Indicator “Contract splitting under the threshold”: 3 contracts without a procedure in 85–100 % threshold for 2022-Q4, 133,443 UAH.

Several contracts to the same supplier, each just under the threshold that requires an open procedure. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Tovarystvo z obmezhenoiu vidpovidalnistiu "Kvorum-Nafta" [32938047]
EDRPOU code
32938047
Buyer
Prybuzhanivska silska rada [04376245] · 2022-Q4
Indicator
Contract splitting under the threshold
Amount
UAH 133,443
Records behind the indicator
3
Found
4 October 2026
Code
UA-1524431

What stands behind it3

  1. Contract

    Date 20 December 2022 · Amount UAH 44,994 · Buyer Prybuzhanivska silska rada [04376245] · Supplier Tovarystvo z obmezhenoiu vidpovidalnistiu "Kvorum-Nafta [32938047] · Ref UA-2022-12-21-008317-a-b1 · procedure: reporting

  2. Contract

    Date 3 November 2022 · Amount UAH 44,334 · Buyer Prybuzhanivska silska rada [04376245] · Supplier Tovarystvo z obmezhenoiu vidpovidalnistiu "Kvorum-Nafta [32938047] · Ref UA-2022-11-07-002110-a-b1 · procedure: reporting

  3. Contract

    Date 3 November 2022 · Amount UAH 44,116 · Buyer Prybuzhanivska silska rada [04376245] · Supplier Tovarystvo z obmezhenoiu vidpovidalnistiu "Kvorum-Nafta [32938047] · Ref UA-2022-11-07-002613-a-c1 · procedure: reporting

Other records of this company15

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 094 October 2026Findings · Duplicate records in the data
  10. 104 October 2026Findings · Contract splitting on one day
All 15
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Contract splitting under the threshold
  4. 144 October 2026Findings · Contract splitting under the threshold
  5. 154 October 2026Findings · Contract splitting under the threshold

JSONFindings · Contract splitting under the threshold