Ukraine · Findings · Procurement plan published late
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "KVORUM-NAFTA" [32938047]
Why it is here
Indicator “Procurement plan published late”: 2 contracts for 6,367,659 UAH signed 2023-02-24…2023-02-24, and the procurement plan was created later — 2023-02-28 (to 7 days after the contract); plan UA-P-2023-02-28-002308-c,UA-P-2023-03-03-000058-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "KVORUM-NAFTA" [32938047]
- EDRPOU code
- 32938047
- Buyer
- Miske komunalne pidpryiemstvo "Mykolaivvodokanal" [31448144]
- Indicator
- Procurement plan published late
- Amount
- UAH 6,367,659
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2587031
- Reference
- 2023-02-24
- Reference
- 2023-02-28
- Reference
- UA-P-2023-02-28-002308-c
- Reference
- UA-P-2023-03-03-000058-a
What stands behind it2
Contract
Date 24 February 2023 · Amount UAH 39,000 · Buyer Miske komunalne pidpryiemstvo "Mykolaivvodokanal [31448144] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "KVORUM-NAFTA [32938047] · Ref UA-2023-03-09-000214-a-b1 · procedure: reporting
Contract
Date 24 February 2023 · Amount UAH 6,421,500 · Buyer Miske komunalne pidpryiemstvo "Mykolaivvodokanal [31448144] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "KVORUM-NAFTA [32938047] · Ref UA-2023-03-09-000051-a-b1 · procedure: reporting
Other records of this company15
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Procurement plan published late
- 084 October 2026Findings · Duplicate records in the data
- 094 October 2026Findings · Contract splitting on one day
- 104 October 2026Findings · Large contract without a procedure
All 15
- 114 October 2026Findings · Large contract without a procedure
- 124 October 2026Findings · Contract splitting under the threshold
- 134 October 2026Findings · Contract splitting under the threshold
- 144 October 2026Findings · Contract splitting under the threshold
- 154 October 2026Findings · Contract splitting under the threshold