WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOV Livain Torh [41449359]

Why it is here

Indicator “Procurement plan published late”: 3 contracts for 4,669,000 UAH signed 2022-04-29…2022-04-29, and the procurement plan was created later — 2022-05-02 (to 3 days after the contract); plan UA-P-2022-05-02-000049-c,UA-P-2022-05-02-000046-b,UA-P-2022-05-02-000239-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV Livain Torh [41449359]
EDRPOU code
41449359
Buyer
AT Vinnytsiaoblenerho [00130694]
Indicator
Procurement plan published late
Amount
UAH 4,669,000
Records behind the indicator
3
Found
5 October 2026
Code
UA-2560088
Reference
2022-04-29
Reference
2022-05-02
Reference
UA-P-2022-05-02-000049-c
Reference
UA-P-2022-05-02-000046-b
Reference
UA-P-2022-05-02-000239-a

What stands behind it3

  1. Contract

    Date 29 April 2022 · Amount UAH 681,700 · Buyer AT Vinnytsiaoblenerho [00130694] · Supplier TOV Livain Torh [41449359] · Ref UA-2022-05-02-000034-b-b1 · procedure: reporting

  2. Contract

    Date 29 April 2022 · Amount UAH 2,424,200 · Buyer AT Vinnytsiaoblenerho [00130694] · Supplier TOV Livain Torh [41449359] · Ref UA-2022-05-02-000038-b-b1 · procedure: reporting

  3. Contract

    Date 29 April 2022 · Amount UAH 1,563,100 · Buyer AT Vinnytsiaoblenerho [00130694] · Supplier TOV Livain Torh [41449359] · Ref UA-2022-05-02-000274-a-c1 · procedure: reporting

Other records of this company25

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 074 October 2026Findings · Duplicate records in the data
  8. 084 October 2026Findings · Duplicate records in the data
  9. 094 October 2026Findings · Contract splitting on one day
  10. 104 October 2026Findings · Contract splitting on one day
All 25
  1. 114 October 2026Findings · Contract splitting on one day
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure
  4. 144 October 2026Findings · Large contract without a procedure
  5. 154 October 2026Findings · Large contract without a procedure
  6. 164 October 2026Findings · Large contract without a procedure
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Contract splitting under the threshold
  9. 194 October 2026Findings · Contract splitting under the threshold
  10. 204 October 2026Findings · Contract splitting under the threshold
  11. 214 October 2026Findings · Contract splitting under the threshold
  12. 224 October 2026Findings · Contract splitting under the threshold
  13. 234 October 2026Findings · Contract splitting under the threshold
  14. 244 October 2026Findings · Contract value inflated by amendments
  15. 254 October 2026Findings · Supplier lives on one buyer without competition

JSONFindings · Procurement plan published late