WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOV "LIVAIN TORH" [41449359]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 4,970,364 UAH signed 2022-03-23…2022-03-23, and the procurement plan was created later — 2022-03-24 (to 1 days after the contract); plan UA-P-2022-03-24-000678-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV "LIVAIN TORH" [41449359]
EDRPOU code
41449359
Buyer
REHIONALNA FILIIA "PRYDNIPROVSKA ZALIZNYTSIA" AKTSIONERNOHO TOVARYSTVA "UKRAINSKA ZALIZNYTSIA" [40081237]
Indicator
Procurement plan published late
Amount
UAH 4,970,364
Records behind the indicator
1
Found
5 October 2026
Code
UA-2539904
Reference
2022-03-23
Reference
2022-03-24
Reference
UA-P-2022-03-24-000678-c

What stands behind it1

  1. Contract

    Date 23 March 2022 · Amount UAH 4,970,364 · Buyer REHIONALNA FILIIA "PRYDNIPROVSKA ZALIZNYTSIA" AKTSIONERNOHO TOVARYSTVA "UKRAINSKA ZALIZNYTSIA [40081237] · Supplier TOV "LIVAIN TORH [41449359] · Ref UA-2022-03-25-000676-c-c1 · procedure: reporting

Other records of this company25

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 074 October 2026Findings · Duplicate records in the data
  8. 084 October 2026Findings · Duplicate records in the data
  9. 094 October 2026Findings · Contract splitting on one day
  10. 104 October 2026Findings · Contract splitting on one day
All 25
  1. 114 October 2026Findings · Contract splitting on one day
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure
  4. 144 October 2026Findings · Large contract without a procedure
  5. 154 October 2026Findings · Large contract without a procedure
  6. 164 October 2026Findings · Large contract without a procedure
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Contract splitting under the threshold
  9. 194 October 2026Findings · Contract splitting under the threshold
  10. 204 October 2026Findings · Contract splitting under the threshold
  11. 214 October 2026Findings · Contract splitting under the threshold
  12. 224 October 2026Findings · Contract splitting under the threshold
  13. 234 October 2026Findings · Contract splitting under the threshold
  14. 244 October 2026Findings · Contract value inflated by amendments
  15. 254 October 2026Findings · Supplier lives on one buyer without competition

JSONFindings · Procurement plan published late