WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO" [00131529]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 45,000 UAH signed 2021-12-29…2021-12-29, and the procurement plan was created later — 2022-01-31 (to 33 days after the contract); plan UA-P-2022-01-31-015266-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO" [00131529]
EDRPOU code
00131529
Buyer
Novoselytskyi zaklad doshkilnoi osvity (iasla-sadok) Neresnytskoi silskoi rady Tiachivskoho raionu Zakarpatskoi oblasti [26395355]
Indicator
Procurement plan published late
Amount
UAH 45,000
Records behind the indicator
1
Found
5 October 2026
Code
UA-2484428
Reference
2021-12-29
Reference
2022-01-31
Reference
UA-P-2022-01-31-015266-b

What stands behind it1

  1. Contract

    Date 29 December 2021 · Amount UAH 45,000 · Buyer Novoselytskyi zaklad doshkilnoi osvity (iasla-sadok) Neresnytskoi silskoi rady Tiachivskoho raionu Zakarpatskoi oblasti [26395355] · Supplier PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO [00131529] · Ref UA-2022-01-31-011306-b-b1 · procedure: reporting

Other records of this company26

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan split into parts
  5. 055 October 2026Findings · Procurement plan split into parts
  6. 065 October 2026Findings · Procurement plan split into parts
  7. 075 October 2026Findings · Procurement plan split into parts
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 105 October 2026Findings · Procurement plan published late
All 26
  1. 115 October 2026Findings · Procurement plan published late
  2. 125 October 2026Findings · Procurement plan published late
  3. 134 October 2026Findings · Contract splitting on one day
  4. 144 October 2026Findings · Contract splitting on one day
  5. 154 October 2026Findings · Contract splitting on one day
  6. 164 October 2026Findings · Contract splitting on one day
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Large contract without a procedure
  9. 194 October 2026Findings · Large contract without a procedure
  10. 204 October 2026Findings · Large contract without a procedure
  11. 214 October 2026Findings · Large contract without a procedure
  12. 224 October 2026Findings · Large contract without a procedure
  13. 234 October 2026Findings · Large contract without a procedure
  14. 244 October 2026Findings · Large contract without a procedure
  15. 254 October 2026Findings · Large contract without a procedure
  16. 264 October 2026Findings · Contract value inflated by amendments

Findings · Procurement plan published late