Ukraine · Findings · Large contract without a procedure
PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO" [00131529]
Why it is here
Indicator “Large contract without a procedure”: contract UA-2026-05-19-012763-a-a1 from 2026-05-14 for 11,098,992 UAH, signed without a procedure (contract report).
A large contract signed without a competitive procedure. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO" [00131529]
- EDRPOU code
- 00131529
- Buyer
- DEPARTAMENT MISKOI INFRASTRUKTURY UZHHORODSKOI MISKOI RADY [36541721] · UA-2026-05-19-012763-a-a1
- Indicator
- Large contract without a procedure
- Amount
- UAH 11,098,992
- Records behind the indicator
- 1
- Found
- 4 October 2026
- Code
- UA-09914
- Reference
- UA-2026-05-19-012763-a-a1
- Reference
- 2026-05-14
What stands behind it1
Contract
Nestandartne pryiednannia do elektrychnykh merezh systemy rozpodilu "pid kliuch" (Budivnytstvo avtotransportnoi bazy dlia KP "Uzhhorodskyi munitsypalnyi transport" Uzhhorodskoi miskoi rady)
Date 19 May 2026 · Amount UAH 11,098,992 · Buyer DEPARTAMENT MISKOI INFRASTRUKTURY UZHHORODSKOI MISKOI RADY [36541721] · Ref UA-2026-05-19-012763-a-a1 · procedure: reporting
Other records of this company30
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Procurement plan published late
- 085 October 2026Findings · Procurement plan published late
- 095 October 2026Findings · Procurement plan published late
- 105 October 2026Findings · Procurement plan published late
All 30
- 115 October 2026Findings · Procurement plan published late
- 125 October 2026Findings · Procurement plan split into parts
- 135 October 2026Findings · Procurement plan split into parts
- 145 October 2026Findings · Procurement plan split into parts
- 154 October 2026Findings · Duplicate records in the data
- 164 October 2026Findings · Duplicate records in the data
- 174 October 2026Findings · Duplicate records in the data
- 184 October 2026Findings · Contract splitting on one day
- 194 October 2026Findings · Contract splitting on one day
- 204 October 2026Findings · Contract splitting on one day
- 214 October 2026Findings · Contract splitting on one day
- 224 October 2026Findings · Large contract without a procedure
- 234 October 2026Findings · Large contract without a procedure
- 244 October 2026Findings · Large contract without a procedure
- 254 October 2026Findings · Large contract without a procedure
- 264 October 2026Findings · Large contract without a procedure
- 274 October 2026Findings · Large contract without a procedure
- 284 October 2026Findings · Large contract without a procedure
- 294 October 2026Findings · Large contract without a procedure
- 304 October 2026Findings · Contract value inflated by amendments