Upravlinnia politsii okhorony v CHerkaskii oblasti [40109037]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 19,965 UAH signed 2021-11-03…2023-12-04, and the procurement plan was created later — 2022-02-01 (to 90 days after the contract); plan UA-P-2022-02-01-001554-c,UA-P-2023-12-05-000263-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Upravlinnia politsii okhorony v CHerkaskii oblasti [40109037]
EDRPOU code
40109037
Buyer
UKP "Komunalnyk" [03366285]
Indicator
Procurement plan published late
Amount
UAH 19,965
Records behind the indicator
2
Found
5 October 2026
Code
UA-2644700
Reference
2021-11-03
Reference
2023-12-04
Reference
2022-02-01
Reference
UA-P-2022-02-01-001554-c
Reference
UA-P-2023-12-05-000263-b

What stands behind it2

  1. Contract

    Date 4 December 2023 · Amount UAH 19,295 · Buyer UKP "Komunalnyk [03366285] · Supplier Upravlinnia politsii okhorony v CHerkaskii oblasti [40109037] · Ref UA-2023-12-05-000718-a-c1 · procedure: reporting

  2. Contract

    Date 3 November 2021 · Amount UAH 670 · Buyer UKP "Komunalnyk [03366285] · Supplier Upravlinnia politsii okhorony v CHerkaskii oblasti [40109037] · Ref UA-2022-02-01-001334-a-c1 · procedure: reporting

Other records of this company9

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 064 October 2026Findings · Contract splitting on one day
  7. 074 October 2026Findings · Procurement under monitoring of the State Audit Service
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure

Findings · Procurement plan published late