WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Upravlinnia politsii okhorony v Sumskii oblasti [40108871]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 17,923 UAH signed 2023-02-03…2023-11-08, and the procurement plan was created later — 2023-04-03 (to 59 days after the contract); plan UA-P-2023-04-03-003362-b,UA-P-2023-11-09-000377-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Upravlinnia politsii okhorony v Sumskii oblasti [40108871]
EDRPOU code
40108871
Buyer
Putyvlskyi litsei №1 im.R. Rudnieva Putyvlskoi miskoi rady [24011451]
Indicator
Procurement plan published late
Amount
UAH 17,923
Records behind the indicator
2
Found
5 October 2026
Code
UA-2644520
Reference
2023-02-03
Reference
2023-11-08
Reference
2023-04-03
Reference
UA-P-2023-04-03-003362-b
Reference
UA-P-2023-11-09-000377-c

What stands behind it2

  1. Contract

    Date 8 November 2023 · Amount UAH 16,723 · Buyer Putyvlskyi litsei №1 im.R. Rudnieva Putyvlskoi miskoi rady [24011451] · Supplier Upravlinnia politsii okhorony v Sumskii oblasti [40108871] · Ref UA-2023-11-09-001007-a-a1 · procedure: reporting

  2. Contract

    Date 3 February 2023 · Amount UAH 1,200 · Buyer Putyvlskyi litsei №1 im.R. Rudnieva Putyvlskoi miskoi rady [24011451] · Supplier Upravlinnia politsii okhorony v Sumskii oblasti [40108871] · Ref UA-2023-04-03-007019-a-c1 · procedure: reporting

Other records of this company19

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 105 October 2026Findings · Procurement plan published late
All 19
  1. 115 October 2026Findings · Procurement plan published late
  2. 124 October 2026Findings · Procurement under monitoring of the State Audit Service
  3. 134 October 2026Findings · Procurement under monitoring of the State Audit Service
  4. 144 October 2026Findings · Procurement under monitoring of the State Audit Service
  5. 154 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 164 October 2026Findings · Procurement under monitoring of the State Audit Service
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Large contract without a procedure
  9. 194 October 2026Findings · Large contract without a procedure

Findings · Procurement plan published late