Indicator “Procurement plan published late”: 3 contracts for 29,360 UAH signed 2022-02-08…2023-01-31, and the procurement plan was created later — 2022-02-10 (to 62 days after the contract); plan UA-P-2022-02-10-002174-b,UA-P-2022-02-10-002357-b,UA-P-2023-04-03-002483-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Upravlinnia politsii okhorony CHernivetskoi oblasti [40108976]
EDRPOU code
40108976
Buyer
KOMUNALNYI ZAKLAD "CHERNIVETSKYI OBLASNYI MUZEI NARODNOI ARKHITEKTURY TA POBUTU" [05534350]
Indicator
Procurement plan published late
Amount
UAH 29,360
Records behind the indicator
3
Found
5 October 2026
Code
UA-2644144
Reference
2022-02-08
Reference
2023-01-31
Reference
2022-02-10
Reference
UA-P-2022-02-10-002174-b
Reference
UA-P-2022-02-10-002357-b
Reference
UA-P-2023-04-03-002483-a

What stands behind it3

  1. Contract

    Date 31 January 2023 · Amount UAH 1,280 · Buyer KOMUNALNYI ZAKLAD "CHERNIVETSKYI OBLASNYI MUZEI NARODNOI ARKHITEKTURY TA POBUTU [05534350] · Supplier UPRAVLINNIA POLITSII OKHORONY V CHERNIVETSKII OBLASTI [40108976] · Ref UA-2023-04-03-006614-a-c1 · procedure: reporting

  2. Contract

    Date 8 February 2022 · Amount UAH 22,080 · Buyer KOMUNALNYI ZAKLAD "CHERNIVETSKYI OBLASNYI MUZEI NARODNOI ARKHITEKTURY TA POBUTU [05534350] · Supplier Upravlinnia politsii okhorony CHernivetskoi oblasti [40108976] · Ref UA-2022-02-10-002624-b-b1 · procedure: reporting

  3. Contract

    Date 8 February 2022 · Amount UAH 6,000 · Buyer KOMUNALNYI ZAKLAD "CHERNIVETSKYI OBLASNYI MUZEI NARODNOI ARKHITEKTURY TA POBUTU [05534350] · Supplier Upravlinnia politsii okhorony CHernivetskoi oblasti [40108976] · Ref UA-2022-02-10-002756-b-b1 · procedure: reporting