WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

UPRAVLINNIA POLITSII OKHORONY V CHERNIVETSKII OBLASTI [40108976]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 7,285 UAH signed 2022-12-15…2022-12-15, and the procurement plan was created later — 2023-08-16 (to 244 days after the contract); plan UA-P-2023-08-16-004669-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
UPRAVLINNIA POLITSII OKHORONY V CHERNIVETSKII OBLASTI [40108976]
EDRPOU code
40108976
Buyer
CHernivetskyi fakhovyi koledzh tekhnolohii ta dyzainu [00301990]
Indicator
Procurement plan published late
Amount
UAH 7,285
Records behind the indicator
1
Found
5 October 2026
Code
UA-2643542
Reference
2022-12-15
Reference
2023-08-16
Reference
UA-P-2023-08-16-004669-b

What stands behind it1

  1. Contract

    Date 15 December 2022 · Amount UAH 7,285 · Buyer CHernivetskyi fakhovyi koledzh tekhnolohii ta dyzainu [00301990] · Supplier UPRAVLINNIA POLITSII OKHORONY V CHERNIVETSKII OBLASTI [40108976] · Ref UA-2023-08-16-009010-a-b1 · procedure: reporting

Other records of this company13

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Contract splitting under the threshold
  7. 074 October 2026Findings · Contract splitting under the threshold
  8. 084 October 2026Findings · Contract splitting under the threshold
  9. 094 October 2026Findings · Contract splitting under the threshold
  10. 104 October 2026Findings · Contract splitting under the threshold
All 13
  1. 114 October 2026Findings · Contract splitting under the threshold
  2. 124 October 2026Findings · Contract splitting under the threshold
  3. 134 October 2026Findings · Contract value inflated by amendments

Findings · Procurement plan published late