WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

UPRAVLINNIA POLITSII OKHORONY V KYIVSKII OBLASTI [40109063]

Why it is here

Indicator “Procurement plan published late”: 3 contracts for 13,526 UAH signed 2023-10-01…2023-10-20, and the procurement plan was created later — 2023-11-06 (to 36 days after the contract); plan UA-P-2023-11-06-004807-c,UA-P-2023-11-06-005123-a,UA-P-2023-11-06-005091-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
UPRAVLINNIA POLITSII OKHORONY V KYIVSKII OBLASTI [40109063]
EDRPOU code
40109063
Buyer
Kyivska filiia Tovarystva z obmezhenoiu vidpovidalnistiu «Hazorozpodilni merezhi Ukrainy» [45385755]
Indicator
Procurement plan published late
Amount
UAH 13,526
Records behind the indicator
3
Found
5 October 2026
Code
UA-2643013
Reference
2023-10-01
Reference
2023-10-20
Reference
2023-11-06
Reference
UA-P-2023-11-06-004807-c
Reference
UA-P-2023-11-06-005123-a
Reference
UA-P-2023-11-06-005091-a

What stands behind it3

  1. Contract

    Date 20 October 2023 · Amount UAH 2,220 · Buyer Kyivska filiia Tovarystva z obmezhenoiu vidpovidalnistiu «Hazorozpodilni merezhi Ukrainy [45385755] · Supplier UPRAVLINNIA POLITSII OKHORONY V KYIVSKII OBLASTI [40109063] · Ref UA-2023-11-07-000469-a-c1 · procedure: reporting

  2. Contract

    Date 20 October 2023 · Amount UAH 4,106 · Buyer Kyivska filiia Tovarystva z obmezhenoiu vidpovidalnistiu «Hazorozpodilni merezhi Ukrainy [45385755] · Supplier UPRAVLINNIA POLITSII OKHORONY V KYIVSKII OBLASTI [40109063] · Ref UA-2023-11-07-000747-a-b1 · procedure: reporting

  3. Contract

    Date 1 October 2023 · Amount UAH 7,200 · Buyer Kyivska filiia Tovarystva z obmezhenoiu vidpovidalnistiu «Hazorozpodilni merezhi Ukrainy [45385755] · Supplier UPRAVLINNIA POLITSII OKHORONY V KYIVSKII OBLASTI [40109063] · Ref UA-2023-11-07-000990-a-c1 · procedure: reporting

Other records of this company18

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 044 October 2026Findings · Contract splitting on one day
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Large contract without a procedure
  7. 074 October 2026Findings · Large contract without a procedure
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Large contract without a procedure
All 18
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure
  4. 144 October 2026Findings · Large contract without a procedure
  5. 154 October 2026Findings · Large contract without a procedure
  6. 164 October 2026Findings · Large contract without a procedure
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Contract splitting under the threshold

Findings · Procurement plan published late