Tovarystvo z obmezhenoiu vidpovid­alnistiu «PAIP TEKHNOLODZHI» [45030983]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 12,254 UAH signed 2023-01-01…2023-01-01, and the procurement plan was created later — 2023-11-23 (to 326 days after the contract); plan UA-P-2023-11-23-006009-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Tovarystvo z obmezhenoiu vidpovid­alnistiu «PAIP TEKHNOLODZHI» [45030983]
EDRPOU code
45030983
Buyer
KP "CHuhuivvoda" [36555336]
Indicator
Procurement plan published late
Amount
UAH 12,254
Records behind the indicator
1
Found
5 October 2026
Code
UA-2630354
Reference
2023-01-01
Reference
2023-11-23
Reference
UA-P-2023-11-23-006009-a

What stands behind it1

  1. Contract

    Date 1 January 2023 · Amount UAH 12,254 · Buyer KP "CHuhuivvoda [36555336] · Supplier Tovarystvo z obmezhenoiu vidpovid­alnistiu «PAIP TEKHNOLODZHI [45030983] · Ref UA-2023-11-23-012874-a-a1 · procedure: reporting

Other records of this company10

  1. 014 October 2026Findings · Procurement under monitoring of the State Audit Service
  2. 024 October 2026Findings · Procurement under monitoring of the State Audit Service
  3. 034 October 2026Findings · Procurement under monitoring of the State Audit Service
  4. 044 October 2026Findings · Procurement under monitoring of the State Audit Service
  5. 054 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 064 October 2026Findings · Large contract without a procedure
  7. 074 October 2026Findings · Supplier registered shortly before the contract
  8. 084 October 2026Findings · Contract value inflated by amendments
  9. 094 October 2026Findings · Contract value inflated by amendments
  10. 104 October 2026Findings · Contract value inflated by amendments

Findings · Procurement plan published late