Ukraine · Findings · Procurement plan published late

TzOV "OKKO-POSTACH" [39263391]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 1,886,000 UAH signed 2022-12-12…2022-12-12, and the procurement plan was created later — 2022-12-17 (to 5 days after the contract); plan UA-P-2022-12-17-000120-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TzOV "OKKO-POSTACH" [39263391]
EDRPOU code
39263391
Buyer
KOMUNALNE PIDPRYIEMSTVO ELEKTRYCHNYKH MEREZH ZOVNISHNOHO OSVITLENNIA "ODEUMISKSVITLO" [03350568]
Indicator
Procurement plan published late
Amount
UAH 1,886,000
Records behind the indicator
1
Found
5 October 2026
Code
UA-2626482
Reference
2022-12-12
Reference
2022-12-17
Reference
UA-P-2022-12-17-000120-b

What stands behind it1

  1. Contract

    Date 12 December 2022 · Amount UAH 1,886,000 · Buyer KOMUNALNE PIDPRYIEMSTVO ELEKTRYCHNYKH MEREZH ZOVNISHNOHO OSVITLENNIA "ODESMISKSVITLO [03350568] · Supplier TzOV "OKKO-POSTACH [39263391] · Ref UA-2022-12-17-000306-a-c1 · procedure: reporting

Other records of this company13

  1. 015 October 2026Findings · Procurement plan published late
  2. 024 October 2026Findings · Contract splitting under the threshold
  3. 034 October 2026Findings · Contract splitting under the threshold
  4. 044 October 2026Findings · Contract splitting under the threshold
  5. 054 October 2026Findings · Contract splitting under the threshold
  6. 064 October 2026Findings · Contract splitting under the threshold
  7. 074 October 2026Findings · Contract splitting under the threshold
  8. 084 October 2026Findings · Contract splitting under the threshold
  9. 094 October 2026Findings · Contract splitting under the threshold
  10. 104 October 2026Findings · Contract splitting under the threshold
All 13
  1. 114 October 2026Findings · Contract splitting under the threshold
  2. 124 October 2026Findings · Contract splitting under the threshold
  3. 134 October 2026Findings · Contract splitting under the threshold

JSONFindings · Procurement plan published late