Indicator “Procurement plan published late”: 2 contracts for 1,830,000 UAH signed 2023-04-07…2023-04-07, and the procurement plan was created later — 2023-04-11 (to 4 days after the contract); plan UA-P-2023-04-11-000677-b,UA-P-2023-04-11-000923-b.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "UKRNAFTA-POSTACH" [43012009]
- EDRPOU code
- 43012009
- Buyer
- Tovarysto z obmezhenoiu vidpovidalnistiu "Kremenchutska TETS" [42225136]
- Indicator
- Procurement plan published late
- Amount
- UAH 1,830,000
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2612558
- Reference
- 2023-04-07
- Reference
- 2023-04-11
- Reference
- UA-P-2023-04-11-000677-b
- Reference
- UA-P-2023-04-11-000923-b
What stands behind it2
Contract
Date 7 April 2023 · Amount UAH 940,000 · Buyer Tovarysto z obmezhenoiu vidpovidalnistiu "Kremenchutska TETS [42225136] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "UKRNAFTA-POSTACH [43012009] · Ref UA-2023-04-11-002133-a-b1 · procedure: reporting
Contract
Date 7 April 2023 · Amount UAH 890,000 · Buyer Tovarysto z obmezhenoiu vidpovidalnistiu "Kremenchutska TETS [42225136] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "UKRNAFTA-POSTACH [43012009] · Ref UA-2023-04-11-002512-a-c1 · procedure: reporting
Other records of this company26
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 074 October 2026Findings · Duplicate records in the data
- 084 October 2026Findings · Duplicate records in the data
- 094 October 2026Findings · Duplicate records in the data
- 104 October 2026Findings · Duplicate records in the data
All 26
- 114 October 2026Findings · Contract splitting on one day
- 124 October 2026Findings · Contract splitting on one day
- 134 October 2026Findings · Procurement under monitoring of the State Audit Service
- 144 October 2026Findings · Procurement under monitoring of the State Audit Service
- 154 October 2026Findings · Procurement under monitoring of the State Audit Service
- 164 October 2026Findings · Procurement under monitoring of the State Audit Service
- 174 October 2026Findings · Large contract without a procedure
- 184 October 2026Findings · Large contract without a procedure
- 194 October 2026Findings · Contract splitting under the threshold
- 204 October 2026Findings · Contract splitting under the threshold
- 214 October 2026Findings · Contract value inflated by amendments
- 224 October 2026Findings · Contract value inflated by amendments
- 234 October 2026Findings · Contract value inflated by amendments
- 244 October 2026Findings · Contract value inflated by amendments
- 254 October 2026Findings · Contract value inflated by amendments
- 264 October 2026Findings · Supplier in the register of debtors