Indicator “Procurement plan published late”: 2 contracts for 35,030 UAH signed 2022-02-28…2022-03-31, and the procurement plan was created later — 2022-04-13 (to 44 days after the contract); plan UA-P-2022-04-13-000955-b,UA-P-2022-04-14-001069-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "TEKHNOHAZ-S" [43287900]
EDRPOU code
43287900
Buyer
Komunalne nekomertsiine pidpryiemstvo "Klinichnyi polohovyi budynok Presviatoi Divy Marii" Sumskoi miskoi rady [02000323]
Indicator
Procurement plan published late
Amount
UAH 35,030
Records behind the indicator
2
Found
5 October 2026
Code
UA-2609483
Reference
2022-02-28
Reference
2022-03-31
Reference
2022-04-13
Reference
UA-P-2022-04-13-000955-b
Reference
UA-P-2022-04-14-001069-b

What stands behind it2

  1. Contract

    Date 31 March 2022 · Amount UAH 31,000 · Buyer Komunalne nekomertsiine pidpryiemstvo "Klinichnyi polohovyi budynok Presviatoi Divy Marii" Sumskoi miskoi rady [02000323] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "TEKHNOHAZ-S [43287900] · Ref UA-2022-04-14-001107-b-b1 · procedure: reporting

  2. Contract

    Date 28 February 2022 · Amount UAH 4,030 · Buyer Komunalne nekomertsiine pidpryiemstvo "Klinichnyi polohovyi budynok Presviatoi Divy Marii" Sumskoi miskoi rady [02000323] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "TEKHNOHAZ-S [43287900] · Ref UA-2022-04-13-000930-b-b1 · procedure: reporting

Other records of this company3

  1. 015 October 2026Findings · Procurement plan published late
  2. 024 October 2026Findings · Contract splitting on one day
  3. 034 October 2026Findings · Contract splitting on one day

Findings · Procurement plan published late