Ukraine · Findings · Procurement plan published late
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ROMUS-POLIHRAF" [25551379]
Why it is here
Indicator “Procurement plan published late”: 3 contracts for 18,974 UAH signed 2022-02-08…2022-12-09, and the procurement plan was created later — 2022-02-09 (to 123 days after the contract); plan UA-P-2022-02-09-002791-b,UA-P-2023-03-06-006125-c,UA-P-2023-03-07-003842-c.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ROMUS-POLIHRAF" [25551379]
- EDRPOU code
- 25551379
- Buyer
- Haluzevyi derzhavnyi arkhiv Ministerstva oborony Ukrainy [14302549]
- Indicator
- Procurement plan published late
- Amount
- UAH 18,974
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2603906
- Reference
- 2022-02-08
- Reference
- 2022-12-09
- Reference
- 2022-02-09
- Reference
- UA-P-2022-02-09-002791-b
- Reference
- UA-P-2023-03-06-006125-c
- Reference
- UA-P-2023-03-07-003842-c
What stands behind it3
Contract
Date 9 December 2022 · Amount UAH 5,974 · Buyer Haluzevyi derzhavnyi arkhiv Ministerstva oborony Ukrainy [14302549] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ROMUS-POLIHRAF [25551379] · Ref UA-2023-03-07-011217-a-a1 · procedure: reporting
Contract
Date 3 November 2022 · Amount UAH 10,000 · Buyer Haluzevyi derzhavnyi arkhiv Ministerstva oborony Ukrainy [14302549] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ROMUS-POLIHRAF [25551379] · Ref UA-2023-03-06-012365-a-b1 · procedure: reporting
Contract
Date 8 February 2022 · Amount UAH 3,000 · Buyer Haluzevyi derzhavnyi arkhiv Ministerstva oborony Ukrainy [14302549] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ROMUS-POLIHRAF [25551379] · Ref UA-2022-02-09-002667-b-b1 · procedure: reporting
Other records of this company20
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 064 October 2026Findings · Contract splitting on one day
- 074 October 2026Findings · Contract splitting under the threshold
- 084 October 2026Findings · Contract splitting under the threshold
- 094 October 2026Findings · Contract splitting under the threshold
- 104 October 2026Findings · Contract splitting under the threshold
All 20
- 114 October 2026Findings · Contract splitting under the threshold
- 124 October 2026Findings · Contract splitting under the threshold
- 134 October 2026Findings · Contract splitting under the threshold
- 144 October 2026Findings · Contract splitting under the threshold
- 154 October 2026Findings · Contract splitting under the threshold
- 164 October 2026Findings · Contract splitting under the threshold
- 174 October 2026Findings · Contract splitting under the threshold
- 184 October 2026Findings · Contract splitting under the threshold
- 194 October 2026Findings · Contract splitting under the threshold
- 204 October 2026Findings · Contract splitting under the threshold