Why it is here

Indicator “Procurement plan published late”: 1 contracts for 16,000 UAH signed 2023-01-25…2023-01-25, and the procurement plan was created later — 2023-03-17 (to 51 days after the contract); plan UA-P-2023-03-17-001266-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "RIVNENSKA OBLASNA ENERHOPOSTACHALNA KOMPANIIA" [42101003]
EDRPOU code
42101003
Buyer
KOMUNALNYI ZAKLAD "PUBLICHNA BIBLIOTEKA" KLEVANSKOI SELYSHCHNOI RADY [44486681]
Indicator
Procurement plan published late
Amount
UAH 16,000
Records behind the indicator
1
Found
5 October 2026
Code
UA-2602557
Reference
2023-01-25
Reference
2023-03-17
Reference
UA-P-2023-03-17-001266-b

What stands behind it1

  1. Contract

    Date 25 January 2023 · Amount UAH 16,000 · Buyer KOMUNALNYI ZAKLAD "PUBLICHNA BIBLIOTEKA" KLEVANSKOI SELYSHCHNOI RADY [44486681] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "RIVNENSKA OBLASNA ENERHOPOSTACHALNA KOMPANIIA [42101003] · Ref UA-2023-03-20-001244-a-c1 · procedure: reporting

Other records of this company24

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Court decisions about the party
  9. 095 October 2026Findings · Plan Over
  10. 104 October 2026Findings · Contract splitting on one day
All 24
  1. 114 October 2026Findings · Contract splitting on one day
  2. 124 October 2026Findings · Contract splitting on one day
  3. 134 October 2026Findings · Contract splitting on one day
  4. 144 October 2026Findings · Procurement under monitoring of the State Audit Service
  5. 154 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 164 October 2026Findings · Procurement under monitoring of the State Audit Service
  7. 174 October 2026Findings · Procurement under monitoring of the State Audit Service
  8. 184 October 2026Findings · Procurement under monitoring of the State Audit Service
  9. 194 October 2026Findings · Procurement under monitoring of the State Audit Service
  10. 204 October 2026Findings · Contract splitting under the threshold
  11. 214 October 2026Findings · Contract splitting under the threshold
  12. 224 October 2026Findings · Contract value inflated by amendments
  13. 234 October 2026Findings · Contract value inflated by amendments
  14. 244 October 2026Findings · Contract value inflated by amendments

Findings · Procurement plan published late