TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ODEUAHROHAZ" [35205975]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 2,909,616 UAH signed 2023-11-20…2023-12-11, and the procurement plan was created later — 2023-11-21 (to 2 days after the contract); plan UA-P-2023-11-21-006048-c,UA-P-2023-12-13-008308-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ODEUAHROHAZ" [35205975]
EDRPOU code
35205975
Buyer
KOMUNALNE PIDPRYIEMSTVO "CHORNOMORSKTEPLOENERHO" CHORNOMORSKOI MISKOI RADY ODEUKOHO RAIONU ODEUKOI OBLASTI [31619819]
Indicator
Procurement plan published late
Amount
UAH 2,909,616
Records behind the indicator
2
Found
5 October 2026
Code
UA-2597888
Reference
2023-11-20
Reference
2023-12-11
Reference
2023-11-21
Reference
UA-P-2023-11-21-006048-c
Reference
UA-P-2023-12-13-008308-a

What stands behind it2

  1. Contract

    Date 11 December 2023 · Amount UAH 1,935,305 · Buyer KOMUNALNE PIDPRYIEMSTVO "CHORNOMORSKTEPLOENERHO" CHORNOMORSKOI MISKOI RADY ODESKOHO RAIONU ODESKOI OBLASTI [31619819] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ODESAHROHAZ [35205975] · Ref UA-2023-12-13-015564-a-c1 · procedure: reporting

  2. Contract

    Date 20 November 2023 · Amount UAH 974,311 · Buyer KOMUNALNE PIDPRYIEMSTVO "CHORNOMORSKTEPLOENERHO" CHORNOMORSKOI MISKOI RADY ODESKOHO RAIONU ODESKOI OBLASTI [31619819] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ODESAHROHAZ [35205975] · Ref UA-2023-11-21-012653-a-a1 · procedure: reporting

Other records of this company14

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 034 October 2026Findings · Duplicate records in the data
  4. 044 October 2026Findings · Contract splitting on one day
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Contract splitting on one day
  7. 074 October 2026Findings · Procurement under monitoring of the State Audit Service
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Large contract without a procedure
All 14
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure
  4. 143 October 2026Findings · Large contract without a procedure

JSONFindings · Procurement plan published late