WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ENERA SUMY" [41884537]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 98,160 UAH signed 2023-02-02…2023-02-02, and the procurement plan was created later — 2023-03-21 (to 47 days after the contract); plan UA-P-2023-03-21-005183-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ENERA SUMY" [41884537]
EDRPOU code
41884537
Buyer
SUMSKYI DOSHKILNYI NAVCHALNYI ZAKLAD (IASLA-SADOK) № 3 "KALYNKA" M.SUMY, SUMSKOI OBLASTI [21114564]
Indicator
Procurement plan published late
Amount
UAH 98,160
Records behind the indicator
1
Found
5 October 2026
Code
UA-2583645
Reference
2023-02-02
Reference
2023-03-21
Reference
UA-P-2023-03-21-005183-b

What stands behind it1

  1. Contract

    Date 2 February 2023 · Amount UAH 98,160 · Buyer SUMSKYI DOSHKILNYI NAVCHALNYI ZAKLAD (IASLA-SADOK) № 3 "KALYNKA" M.SUMY, SUMSKOI OBLASTI [21114564] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ENERA SUMY [41884537] · Ref UA-2023-03-21-010126-a-b1 · procedure: reporting

Other records of this company16

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 105 October 2026Findings · Procurement plan published late
All 16
  1. 114 October 2026Findings · Contract splitting on one day
  2. 124 October 2026Findings · Contract splitting on one day
  3. 134 October 2026Findings · Contract splitting on one day
  4. 144 October 2026Findings · Contract splitting on one day
  5. 154 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 164 October 2026Findings · Court decisions about the party

Findings · Procurement plan published late