WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "VEUT KARD" [43603592]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 156,900 UAH signed 2022-05-17…2022-05-17, and the procurement plan was created later — 2022-07-01 (to 45 days after the contract); plan UA-P-2022-07-01-002207-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "VEUT KARD" [43603592]
EDRPOU code
43603592
Buyer
KOMUNALNE PIDPRYIEMSTVO "AVTOBAZA" RIVNENSKOI OBLASNOI RADY [04014016]
Indicator
Procurement plan published late
Amount
UAH 156,900
Records behind the indicator
1
Found
5 October 2026
Code
UA-2575603
Reference
2022-05-17
Reference
2022-07-01
Reference
UA-P-2022-07-01-002207-b

What stands behind it1

  1. Contract

    Date 17 May 2022 · Amount UAH 156,900 · Buyer KOMUNALNE PIDPRYIEMSTVO "AVTOBAZA" RIVNENSKOI OBLASNOI RADY [04014016] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "VEST KARD [43603592] · Ref UA-2022-07-01-003457-a-b1 · procedure: reporting

Other records of this company14

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 074 October 2026Findings · Contract splitting on one day
  8. 084 October 2026Findings · Procurement under monitoring of the State Audit Service
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Contract splitting under the threshold
All 14
  1. 114 October 2026Findings · Contract splitting under the threshold
  2. 124 October 2026Findings · Contract splitting under the threshold
  3. 134 October 2026Findings · Contract splitting under the threshold