Indicator “Procurement plan published late”: 2 contracts for 1,921,389 UAH signed 2023-04-03…2023-04-03, and the procurement plan was created later — 2023-04-10 (to 7 days after the contract); plan UA-P-2023-04-10-003224-a,UA-P-2023-04-10-003046-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "INZHYNIRYNHOVA KOMPANIIA "ARKON" [41780588]
EDRPOU code
41780588
Buyer
DEPARTAMENT REHIONALNOHO ROZVYTKU ZHYTOMYRSKOI OBLASNOI DERZHAVNOI ADMINISTRATSII [39932654]
Indicator
Procurement plan published late
Amount
UAH 1,921,389
Records behind the indicator
2
Found
5 October 2026
Code
UA-2566284
Reference
2023-04-03
Reference
2023-04-10
Reference
UA-P-2023-04-10-003224-a
Reference
UA-P-2023-04-10-003046-b

What stands behind it2

  1. Contract

    Date 3 April 2023 · Amount UAH 425,486 · Buyer DEPARTAMENT REHIONALNOHO ROZVYTKU ZHYTOMYRSKOI OBLASNOI DERZHAVNOI ADMINISTRATSII [39932654] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "INZHYNIRYNHOVA KOMPANIIA "ARKON [41780588] · Ref UA-2023-04-10-008593-a-b1 · procedure: reporting

  2. Contract

    Date 3 April 2023 · Amount UAH 1,495,903 · Buyer DEPARTAMENT REHIONALNOHO ROZVYTKU ZHYTOMYRSKOI OBLASNOI DERZHAVNOI ADMINISTRATSII [39932654] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "INZHYNIRYNHOVA KOMPANIIA "ARKON [41780588] · Ref UA-2023-04-10-008939-a-c1 · procedure: reporting

Other records of this company10

  1. 015 October 2026Findings · Procurement plan published late
  2. 024 October 2026Findings · Contract splitting on one day
  3. 034 October 2026Findings · Contract splitting on one day
  4. 044 October 2026Findings · Contract splitting on one day
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Contract splitting on one day
  7. 074 October 2026Findings · Large contract without a procedure
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Contract splitting under the threshold

JSONFindings · Procurement plan published late