WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOV HLOBAL SEIL [41915030]

Why it is here

Indicator “Procurement plan published late”: 5 contracts for 103,402 UAH signed 2022-03-25…2022-08-02, and the procurement plan was created later — 2022-06-27 (to 94 days after the contract); plan UA-P-2022-06-27-000538-a,UA-P-2022-06-27-003566-b,UA-P-2022-06-28-002622-b,UA-P-.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV HLOBAL SEIL [41915030]
EDRPOU code
41915030
Buyer
KP SKP "Tashan" [43552543]
Indicator
Procurement plan published late
Amount
UAH 103,402
Records behind the indicator
5
Found
5 October 2026
Code
UA-2559356
Reference
2022-03-25
Reference
2022-08-02
Reference
2022-06-27
Reference
UA-P-2022-06-27-000538-a
Reference
UA-P-2022-06-27-003566-b
Reference
UA-P-2022-06-28-002622-b

What stands behind it5

  1. Contract

    Date 2 August 2022 · Amount UAH 26,704 · Buyer KP SKP "Tashan [43552543] · Supplier TOV HLOBAL SEIL [41915030] · Ref UA-2022-08-18-002863-a-c1 · procedure: reporting

  2. Contract

    Date 16 June 2022 · Amount UAH 18,900 · Buyer KP SKP "Tashan [43552543] · Supplier TOV "Hlobal Seil [41915030] · Ref UA-2022-06-28-004707-a-c1 · procedure: reporting

  3. Contract

    Date 25 May 2022 · Amount UAH 5,690 · Buyer KP SKP "Tashan [43552543] · Supplier TOV "Hlobal Seil [41915030] · Ref UA-2022-06-27-005749-a-a1 · procedure: reporting

  4. Contract

    Date 26 April 2022 · Amount UAH 8,118 · Buyer KP SKP "Tashan [43552543] · Supplier TOV "HLOBAL SEIL [41915030] · Ref UA-2022-07-05-003581-a-a1 · procedure: reporting

  5. Contract

    Date 25 March 2022 · Amount UAH 43,990 · Buyer KP SKP "Tashan [43552543] · Supplier TOV "Hlobap Seil [41915030] · Ref UA-2022-06-27-004820-a-a1 · procedure: reporting

Other records of this company19

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 034 October 2026Findings · Procurement under monitoring of the State Audit Service
  4. 044 October 2026Findings · Procurement under monitoring of the State Audit Service
  5. 054 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 064 October 2026Findings · Procurement under monitoring of the State Audit Service
  7. 074 October 2026Findings · Procurement under monitoring of the State Audit Service
  8. 084 October 2026Findings · Procurement under monitoring of the State Audit Service
  9. 094 October 2026Findings · Procurement under monitoring of the State Audit Service
  10. 104 October 2026Findings · Procurement under monitoring of the State Audit Service
All 19
  1. 114 October 2026Findings · Contract splitting under the threshold
  2. 124 October 2026Findings · Contract splitting under the threshold
  3. 134 October 2026Findings · Contract splitting under the threshold
  4. 144 October 2026Findings · Contract splitting under the threshold
  5. 154 October 2026Findings · Contract splitting under the threshold
  6. 164 October 2026Findings · Contract value inflated by amendments
  7. 174 October 2026Findings · Contract value inflated by amendments
  8. 184 October 2026Findings · Contract value inflated by amendments
  9. 194 October 2026Findings · Contract value inflated by amendments

Findings · Procurement plan published late