Ukraine · Findings · Procurement plan published late
TOV «UKRENERHOBUDPROEKT» [35444619]
Why it is here
Indicator “Procurement plan published late”: 1 contracts for 2,635,716 UAH signed 2023-07-28…2023-07-28, and the procurement plan was created later — 2023-07-31 (to 3 days after the contract); plan UA-P-2023-07-31-001944-b.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOV «UKRENERHOBUDPROEKT» [35444619]
- EDRPOU code
- 35444619
- Buyer
- PRYVATNE AKTSIONERNE TOVARYSTVO "NATSIONALNA ENERHETYCHNA KOMPANIIA "UKRENERHO" [00100227]
- Indicator
- Procurement plan published late
- Amount
- UAH 2,635,716
- Records behind the indicator
- 1
- Found
- 5 October 2026
- Code
- UA-2558288
- Reference
- 2023-07-28
- Reference
- 2023-07-31
- Reference
- UA-P-2023-07-31-001944-b
What stands behind it1
Contract
Date 28 July 2023 · Amount UAH 2,635,716 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO "NATSIONALNA ENERHETYCHNA KOMPANIIA "UKRENERHO [00100227] · Supplier TOV «UKRENERHOBUDPROEKT [35444619] · Ref UA-2023-08-01-001638-a-c1 · procedure: reporting