Why it is here

Indicator “Procurement plan published late”: 2 contracts for 99,600 UAH signed 2021-12-29…2021-12-29, and the procurement plan was created later — 2022-02-02 (to 35 days after the contract); plan UA-P-2022-02-02-003699-a,UA-P-2022-02-02-009807-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV "OOEK" [42114410]
EDRPOU code
42114410
Buyer
TSentr sotsialno-psykholohichnoi reabilitatsii dlia ditei sluzhby u spravakh ditei SHyriaivskoi raiderzhadministratsii [23870991]
Indicator
Procurement plan published late
Amount
UAH 99,600
Records behind the indicator
2
Found
5 October 2026
Code
UA-2544869
Reference
2021-12-29
Reference
2022-02-02
Reference
UA-P-2022-02-02-003699-a
Reference
UA-P-2022-02-02-009807-b

What stands behind it2

  1. Contract

    Date 29 December 2021 · Amount UAH 49,800 · Buyer TSentr sotsialno-psykholohichnoi reabilitatsii dlia ditei sluzhby u spravakh ditei SHyriaivskoi raiderzhadministratsii [23870991] · Supplier TOV "OOEK [42114410] · Ref UA-2022-02-02-001832-a-c1 · procedure: reporting

  2. Contract

    Date 29 December 2021 · Amount UAH 49,800 · Buyer TSentr sotsialno-psykholohichnoi reabilitatsii dlia ditei sluzhby u spravakh ditei SHyriaivskoi raiderzhadministratsii [23870991] · Supplier TOV "OOEK [42114410] · Ref UA-2022-02-02-009475-b-a1 · procedure: reporting

Other records of this company9

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Large contract without a procedure
  7. 074 October 2026Findings · Large contract without a procedure
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Contract value inflated by amendments