TOV "INTEKS INVEUT" [39821153]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 66,300 UAH signed 2022-12-27…2022-12-27, and the procurement plan was created later — 2023-03-22 (to 85 days after the contract); plan UA-P-2023-03-22-003968-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOV "INTEKS INVEUT" [39821153]
EDRPOU code
39821153
Buyer
DP Upravlinnia oboronnoi roboty, zabezpechennia zakonnosti ta pravoporiadku Sumskoi oblasnoi derzhavnoi administratsii [44234231]
Indicator
Procurement plan published late
Amount
UAH 66,300
Records behind the indicator
1
Found
5 October 2026
Code
UA-2526648
Reference
2022-12-27
Reference
2023-03-22
Reference
UA-P-2023-03-22-003968-a

What stands behind it1

  1. Contract

    Date 27 December 2022 · Amount UAH 66,300 · Buyer DP Upravlinnia oboronnoi roboty, zabezpechennia zakonnosti ta pravoporiadku Sumskoi oblasnoi derzhavnoi administratsii [44234231] · Supplier TOV "INTEKS INVEST [39821153] · Ref UA-2023-03-22-006802-a-b1 · procedure: reporting

Other records of this company15

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 064 October 2026Findings · Contract splitting on one day
  7. 074 October 2026Findings · Contract splitting on one day
  8. 084 October 2026Findings · Contract splitting on one day
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Contract splitting under the threshold
All 15
  1. 114 October 2026Findings · Contract splitting under the threshold
  2. 124 October 2026Findings · Contract splitting under the threshold
  3. 134 October 2026Findings · Contract splitting under the threshold
  4. 144 October 2026Findings · Contract splitting under the threshold
  5. 154 October 2026Findings · Contract splitting under the threshold

Findings · Procurement plan published late