WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Sumskyi derzhavnyi universytet [05408289]

Why it is here

Indicator “Procurement plan published late”: 3 contracts for 14,200 UAH signed 2022-04-18…2023-06-12, and the procurement plan was created later — 2022-04-19 (to 42 days after the contract); plan UA-P-2022-04-19-001559-a,UA-P-2023-04-14-000681-a,UA-P-2023-07-24-000422-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Sumskyi derzhavnyi universytet [05408289]
EDRPOU code
05408289
Buyer
KU Komunalna ustanova Sumska himnaziia №1 [14014262]
Indicator
Procurement plan published late
Amount
UAH 14,200
Records behind the indicator
3
Found
5 October 2026
Code
UA-2522237
Reference
2022-04-18
Reference
2023-06-12
Reference
2022-04-19
Reference
UA-P-2022-04-19-001559-a
Reference
UA-P-2023-04-14-000681-a
Reference
UA-P-2023-07-24-000422-a

What stands behind it3

  1. Contract

    Date 12 June 2023 · Amount UAH 400 · Buyer KU Komunalna ustanova Sumska himnaziia №1 [14014262] · Supplier Sumskyi derzhavnyi universytet [05408289] · Ref UA-2023-07-24-002411-a-b1 · procedure: reporting

  2. Contract

    Date 9 March 2023 · Amount UAH 7,800 · Buyer KU Komunalna ustanova Sumska himnaziia №1 [14014262] · Supplier Sumskyi derzhavnyi universytet [05408289] · Ref UA-2023-04-14-006469-a-c1 · procedure: reporting

  3. Contract

    Date 18 April 2022 · Amount UAH 6,000 · Buyer KU Komunalna ustanova Sumska himnaziia №1 [14014262] · Supplier Sumskyi derzhavnyi universytet [05408289] · Ref UA-2022-04-19-000587-c-c1 · procedure: reporting

Other records of this company14

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan split into parts
  5. 055 October 2026Findings · Procurement plan split into parts
  6. 065 October 2026Findings · Procurement plan split into parts
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 104 October 2026Findings · Contract splitting on one day
All 14
  1. 114 October 2026Findings · Contract splitting on one day
  2. 124 October 2026Findings · Contract splitting on one day
  3. 134 October 2026Findings · Contract splitting on one day
  4. 144 October 2026Findings · Contract splitting under the threshold

Findings · Procurement plan published late