WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Pryvatne aktsionerne tovarystvo "Naukovo-doslidnyi instytut prykladnykh informatsiinykh tekhnolohii" [30674051]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 43,875 UAH signed 2023-05-18…2023-05-18, and the procurement plan was created later — 2023-07-13 (to 56 days after the contract); plan UA-P-2023-07-13-005795-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Pryvatne aktsionerne tovarystvo "Naukovo-doslidnyi instytut prykladnykh informatsiinykh tekhnolohii" [30674051]
EDRPOU code
30674051
Buyer
Kyivskyia derzhavna akademiia dekoratyvno-prykladnoho mystetstva i dyzainu imeni Mykhaila Boichuka [21598958]
Indicator
Procurement plan published late
Amount
UAH 43,875
Records behind the indicator
1
Found
5 October 2026
Code
UA-2504075
Reference
2023-05-18
Reference
2023-07-13
Reference
UA-P-2023-07-13-005795-c

What stands behind it1

  1. Contract

    Date 18 May 2023 · Amount UAH 43,875 · Buyer Kyivskyia derzhavna akademiia dekoratyvno-prykladnoho mystetstva i dyzainu imeni Mykhaila Boichuka [21598958] · Supplier Pryvatne aktsionerne tovarystvo "Naukovo-doslidnyi instytut prykladnykh informatsiinykh tekhnolohii [30674051] · Ref UA-2023-07-13-011496-a-c1 · procedure: reporting

Other records of this company9

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 044 October 2026Findings · Large contract without a procedure
  5. 054 October 2026Findings · Large contract without a procedure
  6. 064 October 2026Findings · Large contract without a procedure
  7. 074 October 2026Findings · Large contract without a procedure
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Contract value inflated by amendments

Findings · Procurement plan published late