Ukraine · Findings · Procurement plan published late
PRYVATNE AKTSIONERNE TOVARYSTVO "DTEK KYIVSKI REHIONALNI ELEKTROMEREZHI" [23243188]
Why it is here
Indicator “Procurement plan published late”: 2 contracts for 94,800 UAH signed 2022-02-07…2023-01-26, and the procurement plan was created later — 2022-02-08 (to 47 days after the contract); plan UA-P-2022-02-08-000776-c,UA-P-2023-03-14-000994-c.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- PRYVATNE AKTSIONERNE TOVARYSTVO "DTEK KYIVSKI REHIONALNI ELEKTROMEREZHI" [23243188]
- EDRPOU code
- 23243188
- Buyer
- Komunalne Nekomertsiine Pidpryiemstvo "Piskivskyi TSentr Pervynnoi Medyko-Sanitarnoi Dopomohy" Piskivskoi selyshchnoi rady [42022388]
- Indicator
- Procurement plan published late
- Amount
- UAH 94,800
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2484239
- Reference
- 2022-02-07
- Reference
- 2023-01-26
- Reference
- 2022-02-08
- Reference
- UA-P-2022-02-08-000776-c
- Reference
- UA-P-2023-03-14-000994-c
What stands behind it2
Contract
Date 26 January 2023 · Amount UAH 61,200 · Buyer Komunalne Nekomertsiine Pidpryiemstvo "Piskivskyi TSentr Pervynnoi Medyko-Sanitarnoi Dopomohy" Piskivskoi selyshchnoi r… [42022388] · Supplier PRYVATNE AKTSIONERNE TOVARYSTVO "DTEK KYIVSKI REHIONALNI ELEKTROMEREZHI [23243188] · Ref UA-2023-03-14-002887-a-c1 · procedure: reporting
Contract
Date 7 February 2022 · Amount UAH 33,600 · Buyer KNP Piskivskyi TSPMSD [42022388] · Supplier PAT "DTEK KYIVSKI REHIONALNI ELEKTROMEREZHI [23243188] · Ref UA-2022-02-08-000773-c-a1 · procedure: reporting
Other records of this company17
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 075 October 2026Findings · Procurement plan published late
- 084 October 2026Findings · Contract splitting on one day
- 094 October 2026Findings · Contract splitting on one day
- 104 October 2026Findings · Large contract without a procedure
All 17
- 114 October 2026Findings · Large contract without a procedure
- 124 October 2026Findings · Large contract without a procedure
- 134 October 2026Findings · Large contract without a procedure
- 144 October 2026Findings · Large contract without a procedure
- 154 October 2026Findings · Large contract without a procedure
- 164 October 2026Findings · Supplier terminated in the state register