WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

PAT "Ukrtelekom" [21560766]

Why it is here

Indicator “Procurement plan published late”: 3 contracts for 5,828 UAH signed 2022-01-01…2023-01-01, and the procurement plan was created later — 2022-12-29 (to 362 days after the contract); plan UA-P-2022-12-29-001750-b,UA-P-2023-03-06-000272-c,UA-P-2023-12-05-000372-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
PAT "Ukrtelekom" [21560766]
EDRPOU code
21560766
Buyer
Volynskyi akademichnyi oblasnyi teatr lialok [05384376]
Indicator
Procurement plan published late
Amount
UAH 5,828
Records behind the indicator
3
Found
5 October 2026
Code
UA-2469207
Reference
2022-01-01
Reference
2023-01-01
Reference
2022-12-29
Reference
UA-P-2022-12-29-001750-b
Reference
UA-P-2023-03-06-000272-c
Reference
UA-P-2023-12-05-000372-c

What stands behind it3

  1. Contract

    Date 1 January 2023 · Amount UAH 2,001 · Buyer Volynskyi akademichnyi oblasnyi teatr lialok [05384376] · Supplier PAT "Ukrtelekom [21560766] · Ref UA-2023-03-06-000605-a-b1 · procedure: reporting

  2. Contract

    Date 1 January 2023 · Amount UAH 2,228 · Buyer Volynskyi akademichnyi oblasnyi teatr lialok [05384376] · Supplier AT "Ukrtelekom [21560766] · Ref UA-2023-12-05-000743-a-b1 · procedure: reporting

  3. Contract

    Date 1 January 2022 · Amount UAH 1,600 · Buyer Volynskyi akademichnyi oblasnyi teatr lialok [05384376] · Supplier AT "Ukrtelekom [21560766] · Ref UA-2022-12-29-003599-a-a1 · procedure: reporting

Other records of this company8

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 074 October 2026Findings · Contract splitting on one day
  8. 084 October 2026Findings · Contract splitting on one day

Findings · Procurement plan published late