Indicator “Procurement plan published late”: 2 contracts for 80,613 UAH signed 2022-04-05…2023-07-06, and the procurement plan was created later — 2022-05-26 (to 51 days after the contract); plan UA-P-2022-05-26-001743-b,UA-P-2023-07-07-001050-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- NATSIONALNE AHENTSTVO Z AKREDYTATSII UKRAINY [26196207]
- EDRPOU code
- 26196207
- Buyer
- Komunalne pidpryiemstvo "Dnipropetrovska oblasna stantsiia perelyvannia krovi" [01985434]
- Indicator
- Procurement plan published late
- Amount
- UAH 80,613
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2460703
- Reference
- 2022-04-05
- Reference
- 2023-07-06
- Reference
- 2022-05-26
- Reference
- UA-P-2022-05-26-001743-b
- Reference
- UA-P-2023-07-07-001050-a
What stands behind it2
Contract
Date 6 July 2023 · Amount UAH 65,763 · Buyer Komunalne pidpryiemstvo "Dnipropetrovska oblasna stantsiia perelyvannia krovi [01985434] · Supplier NATSIONALNE AHENTSTVO Z AKREDYTATSII UKRAINY [26196207] · Ref UA-2023-07-07-002983-a-b1 · procedure: reporting
Contract
Date 5 April 2022 · Amount UAH 14,850 · Buyer Komunalne pidpryiemstvo "Dnipropetrovska oblasna stantsiia perelyvannia krovi [01985434] · Supplier NATSIONALNE AHENTSTVO Z AKREDYTATSII UKRAINY [26196207] · Ref UA-2022-05-26-002994-a-b1 · procedure: reporting
Other records of this company9
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 065 October 2026Findings · Procurement plan published late
- 074 October 2026Findings · Contract splitting under the threshold
- 084 October 2026Findings · Contract splitting under the threshold
- 094 October 2026Findings · Contract splitting under the threshold