WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Komunalne pidpryiemstvo "Keruiucha kompaniia z obsluhovuvannia zhytlovoho fondu SHevchenkivskoho raionu m. Kyieva" [34966254]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 1,350 UAH signed 2022-01-28…2022-01-28, and the procurement plan was created later — 2022-07-13 (to 166 days after the contract); plan UA-P-2022-07-13-001108-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Komunalne pidpryiemstvo "Keruiucha kompaniia z obsluhovuvannia zhytlovoho fondu SHevchenkivskoho raionu m. Kyieva" [34966254]
EDRPOU code
34966254
Buyer
HROMADSKA ORHANIZATSIIA FUNDATSIIA SUSPILNO-PRAVOVYKH KOMUNIKATSII LOHARDS [43229550]
Indicator
Procurement plan published late
Amount
UAH 1,350
Records behind the indicator
1
Found
5 October 2026
Code
UA-2444014
Reference
2022-01-28
Reference
2022-07-13
Reference
UA-P-2022-07-13-001108-a

What stands behind it1

  1. Contract

    Date 28 January 2022 · Amount UAH 1,350 · Buyer HROMADSKA ORHANIZATSIIA FUNDATSIIA SUSPILNO-PRAVOVYKH KOMUNIKATSII LOHARDS [43229550] · Supplier Komunalne pidpryiemstvo "Keruiucha kompaniia z obsluhovuvannia zhytlovoho fondu SHevchenkivskoho raionu m. Kyieva [34966254] · Ref UA-2022-07-15-007211-a-a1 · procedure: reporting

Other records of this company10

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan split into parts
  5. 055 October 2026Findings · Procurement plan split into parts
  6. 065 October 2026Findings · Procurement plan split into parts
  7. 075 October 2026Findings · Procurement plan split into parts
  8. 085 October 2026Findings · Procurement plan split into parts
  9. 095 October 2026Findings · Court decisions about the party
  10. 105 October 2026Findings · Court decisions about the party

Findings · Procurement plan published late