Indicator “Procurement plan published late”: 3 contracts for 15,726 UAH signed 2023-05-29…2023-08-10, and the procurement plan was created later — 2023-07-21 (to 70 days after the contract); plan UA-P-2023-07-21-000047-c,UA-P-2023-08-07-001012-b,UA-P-2023-08-15-001383-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
KP "Novovolynskteplokomunenerho" [00185382]
EDRPOU code
00185382
Buyer
Viddil kultury Novovolynskoi miskoi rady Volynskoi oblasti [02227038]
Indicator
Procurement plan published late
Amount
UAH 15,726
Records behind the indicator
3
Found
5 October 2026
Code
UA-2436870
Reference
2023-05-29
Reference
2023-08-10
Reference
2023-07-21
Reference
UA-P-2023-07-21-000047-c
Reference
UA-P-2023-08-07-001012-b
Reference
UA-P-2023-08-15-001383-c

What stands behind it3

  1. Contract

    Date 10 August 2023 · Amount UAH 999 · Buyer Viddil kultury Novovolynskoi miskoi rady Volynskoi oblasti [02227038] · Supplier KP "Novovolynskteplokomunenerho [00185382] · Ref UA-2023-08-15-007047-a-c1 · procedure: reporting

  2. Contract

    Date 19 July 2023 · Amount UAH 13,887 · Buyer Viddil kultury Novovolynskoi miskoi rady Volynskoi oblasti [02227038] · Supplier KP "Novovolynskteplokomunenerho [00185382] · Ref UA-2023-07-21-000157-a-a1 · procedure: reporting

  3. Contract

    Date 29 May 2023 · Amount UAH 839 · Buyer Viddil kultury Novovolynskoi miskoi rady Volynskoi oblasti [02227038] · Supplier KP "Novovolynskteplokomunenerho [00185382] · Ref UA-2023-08-07-002513-a-b1 · procedure: reporting

Other records of this company2

  1. 014 October 2026Findings · Large contract without a procedure
  2. 024 October 2026Findings · Large contract without a procedure

Findings · Procurement plan published late