Ukraine · Findings · Procurement plan published late
KORPORATSIIA "ENERHOREUURS-INVEUT" [30336890]
Why it is here
Indicator “Procurement plan published late”: 3 contracts for 1,128,423 UAH signed 2023-03-02…2023-08-08, and the procurement plan was created later — 2023-03-03 (to 3 days after the contract); plan UA-P-2023-03-03-002899-a,UA-P-2023-03-13-000956-c,UA-P-2023-08-09-001343-c.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- KORPORATSIIA "ENERHOREUURS-INVEUT" [30336890]
- EDRPOU code
- 30336890
- Buyer
- LMKP "Lvivteploenerho" [05506460]
- Indicator
- Procurement plan published late
- Amount
- UAH 1,128,423
- Records behind the indicator
- 3
- Found
- 5 October 2026
- Code
- UA-2434387
- Reference
- 2023-03-02
- Reference
- 2023-08-08
- Reference
- 2023-03-03
- Reference
- UA-P-2023-03-03-002899-a
- Reference
- UA-P-2023-03-13-000956-c
- Reference
- UA-P-2023-08-09-001343-c
What stands behind it3
Contract
Date 8 August 2023 · Amount UAH 954,006 · Buyer LMKP "Lvivteploenerho [05506460] · Supplier KORPORATSIIA "ENERHORESURS-INVEST [30336890] · Ref UA-2023-08-09-006704-a-c1 · procedure: reporting
Contract
Date 10 March 2023 · Amount UAH 149,417 · Buyer LMKP "Lvivteploenerho [05506460] · Supplier KORPORATSIIA "ENERHORESURS-INVEST [30336890] · Ref UA-2023-03-13-002452-a-c1 · procedure: reporting
Contract
Date 2 March 2023 · Amount UAH 25,000 · Buyer LMKP "Lvivteploenerho [05506460] · Supplier KORPORATSIIA "ENERHORESURS-INVEST [30336890] · Ref UA-2023-03-03-007838-a-c1 · procedure: reporting
Other records of this company14
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 055 October 2026Findings · Procurement plan published late
- 064 October 2026Findings · Large contract without a procedure
- 074 October 2026Findings · Large contract without a procedure
- 084 October 2026Findings · Large contract without a procedure
- 094 October 2026Findings · Large contract without a procedure
- 104 October 2026Findings · Contract splitting under the threshold