WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

KOMUNALNE PIDPRYIEMSTVO BROVARSKOI MISKOI RADY BROVARSKOHO RAIONU KYIVSKOI OBLASTI "BROVARYTEPLOVODOENERHIIA" [13711949]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 9,427 UAH signed 2022-07-13…2022-07-13, and the procurement plan was created later — 2022-08-22 (to 40 days after the contract); plan UA-P-2022-08-22-000824-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
KOMUNALNE PIDPRYIEMSTVO BROVARSKOI MISKOI RADY BROVARSKOHO RAIONU KYIVSKOI OBLASTI "BROVARYTEPLOVODOENERHIIA" [13711949]
EDRPOU code
13711949
Buyer
ZAKLAD DOSHKILNOI OSVITY (IASLA-SADOK) KOMBINOVANOHO TYPU "ROMASHKA" BROVARSKOI MISKOI RADY BROVARSKOHO RAIONU KYIVSKOI OBLASTI [25295982]
Indicator
Procurement plan published late
Amount
UAH 9,427
Records behind the indicator
1
Found
5 October 2026
Code
UA-2431923
Reference
2022-07-13
Reference
2022-08-22
Reference
UA-P-2022-08-22-000824-b

What stands behind it1

  1. Contract

    Date 13 July 2022 · Amount UAH 9,427 · Buyer ZAKLAD DOSHKILNOI OSVITY (IASLA-SADOK) KOMBINOVANOHO TYPU "ROMASHKA" BROVARSKOI MISKOI RADY BROVARSKOHO RAIONU KYIVSKOI… [25295982] · Supplier KOMUNALNE PIDPRYIEMSTVO BROVARSKOI MISKOI RADY BROVARSKOHO RAIONU KYIVSKOI OBLASTI "BROVARYTEPLOVODOENERHIIA [13711949] · Ref UA-2022-08-22-001557-a-b1 · procedure: reporting

Other records of this company8

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan split into parts
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Court decisions about the party
  7. 074 October 2026Findings · Supplier terminated in the state register
  8. 084 October 2026Findings · Supplier terminated in the state register

Findings · Procurement plan published late