WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

DERZHAVNE PIDPRYIEMSTVO "SUMSKYI REHIONALNYI NAUKOVO-VYROBNYCHYI TSENTR STANDARTYZATSII, METROLOHII TA SERTYFIKATSII" [02568064]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 3,078 UAH signed 2023-05-12…2023-07-11, and the procurement plan was created later — 2023-12-07 (to 209 days after the contract); plan UA-P-2023-12-07-008059-a,UA-P-2023-12-08-002396-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
DERZHAVNE PIDPRYIEMSTVO "SUMSKYI REHIONALNYI NAUKOVO-VYROBNYCHYI TSENTR STANDARTYZATSII, METROLOHII TA SERTYFIKATSII" [02568064]
EDRPOU code
02568064
Buyer
Sumskyi doshkilnyi navchalnyi zaklad (iasla-sadok) №33 "Marynka" m.Sumy, Sumskoi oblasti [23294464]
Indicator
Procurement plan published late
Amount
UAH 3,078
Records behind the indicator
2
Found
5 October 2026
Code
UA-2405021
Reference
2023-05-12
Reference
2023-07-11
Reference
2023-12-07
Reference
UA-P-2023-12-07-008059-a
Reference
UA-P-2023-12-08-002396-a

What stands behind it2

  1. Contract

    Date 11 July 2023 · Amount UAH 2,807 · Buyer Sumskyi doshkilnyi navchalnyi zaklad (iasla-sadok) №33 "Marynka" m.Sumy, Sumskoi oblasti [23294464] · Supplier DERZHAVNE PIDPRYIEMSTVO "SUMSKYI REHIONALNYI NAUKOVO-VYROBNYCHYI TSENTR STANDARTYZATSII, METROLOHII TA SERTYFIKATSII [02568064] · Ref UA-2023-12-08-006144-a-c1 · procedure: reporting

  2. Contract

    Date 12 May 2023 · Amount UAH 271 · Buyer Sumskyi doshkilnyi navchalnyi zaklad (iasla-sadok) №33 "Marynka" m.Sumy, Sumskoi oblasti [23294464] · Supplier DERZHAVNE PIDPRYIEMSTVO "SUMSKYI REHIONALNYI NAUKOVO-VYROBNYCHYI TSENTR STANDARTYZATSII, METROLOHII TA SERTYFIKATSII [02568064] · Ref UA-2023-12-07-022167-a-c1 · procedure: reporting

Other records of this company4

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late

Findings · Procurement plan published late