WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Aktsionerne tovarystvo «KHarkivoblenerho» [00131954]

Why it is here

Indicator “Procurement plan published late”: 13 contracts for 1,430,573 UAH signed 2023-07-31…2025-12-19, and the procurement plan was created later — 2023-08-02 (to 4 days after the contract); plan UA-P-2023-08-03-003162-a,UA-P-2023-08-02-004347-c,UA-P-2023-08-02-004349-c,UA-P-.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Aktsionerne tovarystvo «KHarkivoblenerho» [00131954]
EDRPOU code
00131954
Buyer
KP "KHarkivskyi metropoliten" [04805918]
Indicator
Procurement plan published late
Amount
UAH 1,430,573
Records behind the indicator
13
Found
5 October 2026
Code
UA-2381937
Reference
2023-07-31
Reference
2025-12-19
Reference
2023-08-02
Reference
UA-P-2023-08-03-003162-a
Reference
UA-P-2023-08-02-004347-c
Reference
UA-P-2023-08-02-004349-c

What stands behind it10

  1. Contract

    Date 24 December 2025 · Amount UAH 1,322,800 · Buyer KP "KHarkivskyi metropoliten [04805918] · Ref UA-2025-12-24-015152-a-c1 · procedure: reporting

  2. Contract

    Date 31 July 2023 · Amount UAH 9,367 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-08-006310-a-c1 · procedure: reporting

  3. Contract

    Date 31 July 2023 · Amount UAH 9,688 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-08-007067-a-c1 · procedure: reporting

  4. Contract

    Date 31 July 2023 · Amount UAH 9,660 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-08-007462-a-c1 · procedure: reporting

  5. Contract

    Date 31 July 2023 · Amount UAH 7,859 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-08-010944-a-c1 · procedure: reporting

  6. Contract

    Date 31 July 2023 · Amount UAH 9,550 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-08-011293-a-c1 · procedure: reporting

  7. Contract

    Date 31 July 2023 · Amount UAH 9,754 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-08-011460-a-c1 · procedure: reporting

  8. Contract

    Date 31 July 2023 · Amount UAH 8,387 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-09-001285-a-a1 · procedure: reporting

  9. Contract

    Date 31 July 2023 · Amount UAH 7,859 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-09-001498-a-a1 · procedure: reporting

  10. Contract

    Date 31 July 2023 · Amount UAH 7,247 · Buyer KP "KHarkivskyi metropoliten [04805918] · Supplier Aktsionerne tovarystvo «KHarkivoblenerho [00131954] · Ref UA-2023-08-09-001687-a-a1 · procedure: reporting

10 of 13 records shown.

Other records of this company69

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 105 October 2026Findings · Procurement plan published late
All 69
  1. 115 October 2026Findings · Procurement plan published late
  2. 125 October 2026Findings · Procurement plan split into parts
  3. 135 October 2026Findings · Procurement plan split into parts
  4. 145 October 2026Findings · Procurement plan split into parts
  5. 155 October 2026Findings · Procurement plan split into parts
  6. 165 October 2026Findings · Procurement plan split into parts
  7. 175 October 2026Findings · Procurement plan split into parts
  8. 185 October 2026Findings · Procurement plan split into parts
  9. 195 October 2026Findings · Procurement plan split into parts
  10. 205 October 2026Findings · Procurement plan split into parts
  11. 215 October 2026Findings · Procurement plan split into parts
  12. 225 October 2026Findings · Procurement plan split into parts
  13. 235 October 2026Findings · Procurement plan split into parts
  14. 245 October 2026Findings · Procurement plan split into parts
  15. 255 October 2026Findings · Procurement plan split into parts
  16. 265 October 2026Findings · Procurement plan split into parts
  17. 275 October 2026Findings · Procurement plan split into parts
  18. 285 October 2026Findings · Procurement plan split into parts
  19. 294 October 2026Findings · Contract splitting on one day
  20. 304 October 2026Findings · Contract splitting on one day
  21. 314 October 2026Findings · Contract splitting on one day
  22. 324 October 2026Findings · Contract splitting on one day
  23. 334 October 2026Findings · Contract splitting on one day
  24. 344 October 2026Findings · Contract splitting on one day
  25. 354 October 2026Findings · Contract splitting on one day
  26. 364 October 2026Findings · Contract splitting on one day
  27. 374 October 2026Findings · Large contract without a procedure
  28. 384 October 2026Findings · Large contract without a procedure
  29. 394 October 2026Findings · Large contract without a procedure
  30. 404 October 2026Findings · Large contract without a procedure
  31. 414 October 2026Findings · Large contract without a procedure
  32. 424 October 2026Findings · Large contract without a procedure
  33. 434 October 2026Findings · Large contract without a procedure
  34. 444 October 2026Findings · Large contract without a procedure
  35. 454 October 2026Findings · Large contract without a procedure
  36. 464 October 2026Findings · Large contract without a procedure
  37. 474 October 2026Findings · Large contract without a procedure
  38. 484 October 2026Findings · Large contract without a procedure
  39. 494 October 2026Findings · Large contract without a procedure
  40. 504 October 2026Findings · Large contract without a procedure
  41. 514 October 2026Findings · Large contract without a procedure
  42. 524 October 2026Findings · Large contract without a procedure
  43. 534 October 2026Findings · Large contract without a procedure
  44. 544 October 2026Findings · Large contract without a procedure
  45. 554 October 2026Findings · Large contract without a procedure
  46. 564 October 2026Findings · Large contract without a procedure
  47. 574 October 2026Findings · Large contract without a procedure
  48. 584 October 2026Findings · Large contract without a procedure
  49. 594 October 2026Findings · Large contract without a procedure
  50. 604 October 2026Findings · Large contract without a procedure
  51. 614 October 2026Findings · Large contract without a procedure
  52. 624 October 2026Findings · Large contract without a procedure
  53. 634 October 2026Findings · Large contract without a procedure
  54. 644 October 2026Findings · Large contract without a procedure
  55. 654 October 2026Findings · Large contract without a procedure
  56. 664 October 2026Findings · Large contract without a procedure
  57. 674 October 2026Findings · Large contract without a procedure
  58. 684 October 2026Findings · Contract splitting under the threshold
  59. 694 October 2026Findings · Contract value inflated by amendments

JSONFindings · Procurement plan published late