WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

Aktsionerne tovarystvo "Operator hazorozpodilnoi systemy "KHarkivmiskhaz" [03359552]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 2,783 UAH signed 2022-02-02…2023-01-19, and the procurement plan was created later — 2022-02-04 (to 35 days after the contract); plan UA-P-2022-02-04-005883-a,UA-P-2023-02-23-001677-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
Aktsionerne tovarystvo "Operator hazorozpodilnoi systemy "KHarkivmiskhaz" [03359552]
EDRPOU code
03359552
Buyer
Viddil kultury po KHolodnohirskomu raionu Departamentu kultury KHarkivskoi miskoi rady [37460591]
Indicator
Procurement plan published late
Amount
UAH 2,783
Records behind the indicator
2
Found
5 October 2026
Code
UA-2380922
Reference
2022-02-02
Reference
2023-01-19
Reference
2022-02-04
Reference
UA-P-2022-02-04-005883-a
Reference
UA-P-2023-02-23-001677-c

What stands behind it2

  1. Contract

    Date 19 January 2023 · Amount UAH 1,041 · Buyer Viddil kultury po KHolodnohirskomu raionu Departamentu kultury KHarkivskoi miskoi rady [37460591] · Supplier Aktsionerne tovarystvo "Operator hazorozpodilnoi systemy "KHarkivmiskhaz [03359552] · Ref UA-2023-02-23-003548-a-b1 · procedure: reporting

  2. Contract

    Date 2 February 2022 · Amount UAH 1,742 · Buyer Viddil kultury po KHolodnohirskomu raionu Departamentu kultury KHarkivskoi miskoi rady [37460591] · Supplier Aktsionerne tovarystvo "Operator hazorozpodilnoi systemy "KHarkivmiskhaz [03359552] · Ref UA-2022-02-04-014523-b-c1 · procedure: reporting

Other records of this company7

  1. 015 October 2026Findings · Procurement plan published late
  2. 024 October 2026Findings · Contract splitting on one day
  3. 034 October 2026Findings · Contract splitting on one day
  4. 044 October 2026Findings · Contract splitting on one day
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Contract splitting on one day
  7. 074 October 2026Findings · Contract splitting under the threshold

Findings · Procurement plan published late