AT VINNYTSIAOBLENERHO [00130694]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 8,394 UAH signed 2023-01-16…2023-06-26, and the procurement plan was created later — 2023-03-14 (to 57 days after the contract); plan UA-P-2023-03-14-002334-b,UA-P-2023-06-29-000115-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
AT VINNYTSIAOBLENERHO [00130694]
EDRPOU code
00130694
Buyer
KZ TSentr nadannia sotsialnykh posluh Horodkivskoi silskoi rady [44059603]
Indicator
Procurement plan published late
Amount
UAH 8,394
Records behind the indicator
2
Found
5 October 2026
Code
UA-2378914
Reference
2023-01-16
Reference
2023-06-26
Reference
2023-03-14
Reference
UA-P-2023-03-14-002334-b
Reference
UA-P-2023-06-29-000115-b

What stands behind it2

  1. Contract

    Date 26 June 2023 · Amount UAH 5,192 · Buyer KZ TSentr nadannia sotsialnykh posluh Horodkivskoi silskoi rady [44059603] · Supplier AKTSIONERNE TOVARSTVO "VINNYTSIAOBLENERHO" SO "Tulchynski ELEKTRYCHNI MEREZHI [00130694] · Ref UA-2023-06-29-003981-a-a1 · procedure: reporting

  2. Contract

    Date 16 January 2023 · Amount UAH 3,202 · Buyer KZ TSentr nadannia sotsialnykh posluh Horodkivskoi silskoi rady [44059603] · Supplier AT VINNYTSIAOBLENERHO [00130694] · Ref UA-2023-03-14-004463-a-b1 · procedure: reporting

Other records of this company10

  1. 015 October 2026Findings · Procurement plan split into parts
  2. 025 October 2026Findings · Procurement plan split into parts
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan split into parts
  5. 055 October 2026Findings · Procurement plan split into parts
  6. 065 October 2026Findings · Procurement plan published late
  7. 074 October 2026Findings · Contract splitting on one day
  8. 084 October 2026Findings · Procurement under monitoring of the State Audit Service