WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

AT "KHersonoblenerho" [05396638]

Why it is here

Indicator “Procurement plan published late”: 2 contracts for 2,488,800 UAH signed 2023-02-13…2023-02-13, and the procurement plan was created later — 2023-02-24 (to 11 days after the contract); plan UA-P-2023-02-24-005081-b,UA-P-2023-02-24-005094-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
AT "KHersonoblenerho" [05396638]
EDRPOU code
05396638
Buyer
KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO "KHERSONSKYI OBLASNYI ONKOLOHICHNYI DYSPANSER" KHERSONSKOI OBLASNOI RADY [02009896]
Indicator
Procurement plan published late
Amount
UAH 2,488,800
Records behind the indicator
2
Found
5 October 2026
Code
UA-2378564
Reference
2023-02-13
Reference
2023-02-24
Reference
UA-P-2023-02-24-005081-b
Reference
UA-P-2023-02-24-005094-b

What stands behind it2

  1. Contract

    Date 13 February 2023 · Amount UAH 156,000 · Buyer KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO "KHERSONSKYI OBLASNYI ONKOLOHICHNYI DYSPANSER" KHERSONSKOI OBLASNOI RADY [02009896] · Supplier AT "KHersonoblenerho [05396638] · Ref UA-2023-02-24-011539-a-b1 · procedure: reporting

  2. Contract

    Date 13 February 2023 · Amount UAH 2,332,800 · Buyer KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO "KHERSONSKYI OBLASNYI ONKOLOHICHNYI DYSPANSER" KHERSONSKOI OBLASNOI RADY [02009896] · Supplier AT "KHersonoblenerho [05396638] · Ref UA-2023-02-24-011558-a-c1 · procedure: reporting

Other records of this company7

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan split into parts
  4. 045 October 2026Findings · Procurement plan split into parts
  5. 055 October 2026Findings · Procurement plan split into parts
  6. 065 October 2026Findings · Procurement plan split into parts
  7. 074 October 2026Findings · Contract splitting under the threshold