Why it is here

Indicator “Procurement plan published late”: 1 contracts for 10,000 UAH signed 2022-03-03…2022-03-03, and the procurement plan was created later — 2022-06-03 (to 92 days after the contract); plan UA-P-2022-06-03-000605-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
AT "Oblteplokomunenerho" [03357671]
EDRPOU code
03357671
Buyer
KU Komunalna ustanova "TSentr nadannia sotsialnykh posluh" Horodnianskoi miskoi rady [43981566]
Indicator
Procurement plan published late
Amount
UAH 10,000
Records behind the indicator
1
Found
5 October 2026
Code
UA-2376551
Reference
2022-03-03
Reference
2022-06-03
Reference
UA-P-2022-06-03-000605-c

What stands behind it1

  1. Contract

    Date 3 March 2022 · Amount UAH 10,000 · Buyer KU Komunalna ustanova "TSentr nadannia sotsialnykh posluh" Horodnianskoi miskoi rady [43981566] · Supplier AT "Oblteplokomunenerho [03357671] · Ref UA-2022-06-03-005862-a-c1 · procedure: reporting

Other records of this company13

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 034 October 2026Findings · Large contract without a procedure
  4. 044 October 2026Findings · Large contract without a procedure
  5. 054 October 2026Findings · Large contract without a procedure
  6. 064 October 2026Findings · Large contract without a procedure
  7. 074 October 2026Findings · Large contract without a procedure
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Large contract without a procedure
All 13
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Large contract without a procedure
  3. 134 October 2026Findings · Large contract without a procedure

Findings · Procurement plan published late