WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "MYKOLAIVHAZ" [05410263]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 45,620 UAH signed 2022-01-01…2022-01-01, and the procurement plan was created later — 2022-02-21 (to 51 days after the contract); plan UA-P-2022-02-21-000779-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "MYKOLAIVHAZ" [05410263]
EDRPOU code
05410263
Buyer
SHEVCHENKIVSKA SILSKA RADA [04375286]
Indicator
Procurement plan published late
Amount
UAH 45,620
Records behind the indicator
1
Found
5 October 2026
Code
UA-2371174
Reference
2022-01-01
Reference
2022-02-21
Reference
UA-P-2022-02-21-000779-b

What stands behind it1

  1. Contract

    Date 1 January 2022 · Amount UAH 45,620 · Buyer SHEVCHENKIVSKA SILSKA RADA [04375286] · Supplier AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "MYKOLAIVHAZ [05410263] · Ref UA-2022-02-21-001010-b-b1 · procedure: reporting

Other records of this company16

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Procurement plan published late
  8. 085 October 2026Findings · Procurement plan published late
  9. 095 October 2026Findings · Procurement plan published late
  10. 105 October 2026Findings · Procurement plan published late
All 16
  1. 115 October 2026Findings · Procurement plan published late
  2. 125 October 2026Findings · Procurement plan published late
  3. 135 October 2026Findings · Procurement plan published late
  4. 145 October 2026Findings · Procurement plan published late
  5. 154 October 2026Findings · Contract splitting on one day
  6. 164 October 2026Findings · Contract splitting on one day

Findings · Procurement plan published late