Indicator “Procurement plan published late”: 3 contracts for 9,690 UAH signed 2022-04-27…2022-09-21, and the procurement plan was created later — 2022-04-28 (to 203 days after the contract); plan UA-P-2022-04-28-000685-a,UA-P-2022-12-12-007105-c,UA-P-2022-12-12-004984-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "SUMYHAZ" [03352432]
EDRPOU code
03352432
Buyer
Upravlinnia arkhitektury ta mistobuduvannia Sumskoi miskoi rady [40462253]
Indicator
Procurement plan published late
Amount
UAH 9,690
Records behind the indicator
3
Found
5 October 2026
Code
UA-2370189
Reference
2022-04-27
Reference
2022-09-21
Reference
2022-04-28
Reference
UA-P-2022-04-28-000685-a
Reference
UA-P-2022-12-12-007105-c
Reference
UA-P-2022-12-12-004984-a

What stands behind it3

  1. Contract

    Date 21 September 2022 · Amount UAH 390 · Buyer Upravlinnia arkhitektury ta mistobuduvannia Sumskoi miskoi rady [40462253] · Supplier AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "SUMYHAZ [03352432] · Ref UA-2022-12-15-015237-a-b1 · procedure: reporting

  2. Contract

    Date 23 May 2022 · Amount UAH 506 · Buyer Upravlinnia arkhitektury ta mistobuduvannia Sumskoi miskoi rady [40462253] · Supplier AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "SUMYHAZ [03352432] · Ref UA-2022-12-15-017774-a-c1 · procedure: reporting

  3. Contract

    Date 27 April 2022 · Amount UAH 8,793 · Buyer Upravlinnia arkhitektury ta mistobuduvannia Sumskoi miskoi rady [40462253] · Supplier AKTSIONERNE TOVARYSTVO "OPERATOR HAZOROZPODILNOI SYSTEMY "SUMYHAZ [03352432] · Ref UA-2022-04-28-000853-a-a1 · procedure: reporting

Other records of this company9

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Court decisions about the party
  6. 065 October 2026Findings · Court decisions about the party
  7. 075 October 2026Findings · Several indicators on one party
  8. 084 October 2026Findings · Link to the register of corruption offenders
  9. 094 October 2026Findings · Link to the register of corruption offenders

Findings · Procurement plan published late