Ukraine · Findings · Procurement plan published late
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU FIRMA "KRIOHENSERVIS" [21543199]
Why it is here
Indicator “Procurement plan published late”: 2 contracts for 155,900 UAH signed 2022-05-17…2022-12-19, and the procurement plan was created later — 2022-12-22 (to 303 days after the contract); plan UA-P-2022-12-22-003129-a,UA-P-2023-03-16-000844-b.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU FIRMA "KRIOHENSERVIS" [21543199]
- EDRPOU code
- 21543199
- Buyer
- KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO «CHERNIHIVSKA MISKA LIKARNIA №2» CHERNIHIVSKOI MISKOI RADY [14233274]
- Indicator
- Procurement plan published late
- Amount
- UAH 155,900
- Records behind the indicator
- 2
- Found
- 5 October 2026
- Code
- UA-2337512
- Reference
- 2022-05-17
- Reference
- 2022-12-19
- Reference
- 2022-12-22
- Reference
- UA-P-2022-12-22-003129-a
- Reference
- UA-P-2023-03-16-000844-b
What stands behind it2
Contract
Date 19 December 2022 · Amount UAH 87,200 · Buyer KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO «CHERNIHIVSKA MISKA LIKARNIA №2» CHERNIHIVSKOI MISKOI RADY [14233274] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU FIRMA "KRIOHENSERVIS [21543199] · Ref UA-2022-12-22-010562-a-a1 · procedure: reporting
Contract
Date 17 May 2022 · Amount UAH 68,700 · Buyer KOMUNALNE NEKOMERTSIINE PIDPRYIEMSTVO «CHERNIHIVSKA MISKA LIKARNIA №2» CHERNIHIVSKOI MISKOI RADY [14233274] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU FIRMA "KRIOHENSERVIS [21543199] · Ref UA-2023-03-16-001908-a-c1 · procedure: reporting
Other records of this company14
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 045 October 2026Findings · Procurement plan published late
- 054 October 2026Findings · Contract splitting on one day
- 064 October 2026Findings · Procurement under monitoring of the State Audit Service
- 074 October 2026Findings · Procurement under monitoring of the State Audit Service
- 084 October 2026Findings · Contract splitting under the threshold
- 094 October 2026Findings · Cartel pattern
- 104 October 2026Findings · Cartel pattern