Ukraine · Findings · Procurement plan published late
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "STRUKTUM" [38186327]
Why it is here
Indicator “Procurement plan published late”: 4 contracts for 223,891,102 UAH signed 2025-11-20…2025-12-11, and the procurement plan was created later — 2025-11-25 (to 5 days after the contract); plan UA-P-2025-11-25-020193-a,UA-P-2025-11-25-020189-a,UA-P-2025-11-25-020191-a,UA-P-.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "STRUKTUM" [38186327]
- EDRPOU code
- 38186327
- Buyer
- Sluzhba vidnovlennia ta rozvytku infrastruktury u CHernihivskii oblasti [25901106]
- Indicator
- Procurement plan published late
- Amount
- UAH 223,891,102
- Records behind the indicator
- 4
- Found
- 5 October 2026
- Code
- UA-2335406
- Reference
- 2025-11-20
- Reference
- 2025-12-11
- Reference
- 2025-11-25
- Reference
- UA-P-2025-11-25-020193-a
- Reference
- UA-P-2025-11-25-020189-a
- Reference
- UA-P-2025-11-25-020191-a
What stands behind it4
Contract
Date 12 December 2025 · Amount UAH 58,845,216 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u CHernihivskii oblasti [25901106] · Ref UA-2025-12-12-000680-a-b1 · procedure: reporting
Contract
Date 25 November 2025 · Amount UAH 62,676,361 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u CHernihivskii oblasti [25901106] · Ref UA-2025-11-25-016731-a-a1 · procedure: reporting
Contract
Date 25 November 2025 · Amount UAH 63,202,555 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u CHernihivskii oblasti [25901106] · Ref UA-2025-11-25-017004-a-c1 · procedure: reporting
Contract
Date 25 November 2025 · Amount UAH 63,759,495 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u CHernihivskii oblasti [25901106] · Ref UA-2025-11-25-017139-a-c1 · procedure: reporting
Other records of this company12
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Court decisions about the party
- 034 October 2026Findings · Large contract without a procedure
- 044 October 2026Findings · Large contract without a procedure
- 054 October 2026Findings · Large contract without a procedure
- 064 October 2026Findings · Large contract without a procedure
- 074 October 2026Findings · Large contract without a procedure
- 084 October 2026Findings · Large contract without a procedure
- 094 October 2026Findings · Large contract without a procedure
- 104 October 2026Findings · Large contract without a procedure