WORLDWIDE‑CORRUPTION

Ukraine · Findings · Procurement plan published late

TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ENERA VINNYTSIA" [41835359]

Why it is here

Indicator “Procurement plan published late”: 1 contracts for 1,502,641 UAH signed 2022-12-23…2022-12-23, and the procurement plan was created later — 2022-12-27 (to 4 days after the contract); plan UA-P-2022-12-27-003604-c.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ENERA VINNYTSIA" [41835359]
EDRPOU code
41835359
Buyer
Upravlinnia vykonavchoi dyrektsii Fondu sotsialnoho strakhuvannia Ukrainy u Vinnytskii oblasti [41315197]
Indicator
Procurement plan published late
Amount
UAH 1,502,641
Records behind the indicator
1
Found
5 October 2026
Code
UA-2331647
Reference
2022-12-23
Reference
2022-12-27
Reference
UA-P-2022-12-27-003604-c

What stands behind it1

  1. Contract

    Date 23 December 2022 · Amount UAH 1,502,641 · Buyer Upravlinnia vykonavchoi dyrektsii Fondu sotsialnoho strakhuvannia Ukrainy u Vinnytskii oblasti [41315197] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "ENERA VINNYTSIA [41835359] · Ref UA-2022-12-27-009718-a-a1 · procedure: reporting

Other records of this company16

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 065 October 2026Findings · Procurement plan published late
  7. 075 October 2026Findings · Court decisions about the party
  8. 085 October 2026Findings · Several indicators on one party
  9. 094 October 2026Findings · Duplicate records in the data
  10. 104 October 2026Findings · Procurement under monitoring of the State Audit Service
All 16
  1. 114 October 2026Findings · Procurement under monitoring of the State Audit Service
  2. 124 October 2026Findings · Procurement under monitoring of the State Audit Service
  3. 134 October 2026Findings · Large contract without a procedure
  4. 144 October 2026Findings · Contract value inflated by amendments
  5. 154 October 2026Findings · Contract value inflated by amendments
  6. 164 October 2026Findings · Supplier in the register of debtors

JSONFindings · Procurement plan published late