Indicator “Procurement plan published late”: 2 contracts for 1,799,238 UAH signed 2022-12-14…2022-12-26, and the procurement plan was created later — 2022-12-15 (to 2 days after the contract); plan UA-P-2022-12-15-000382-b,UA-P-2022-12-28-000226-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "DAREKS-ENERHO" [39423347]
EDRPOU code
39423347
Buyer
KP "Zdolbunivvodokanal" [32256482]
Indicator
Procurement plan published late
Amount
UAH 1,799,238
Records behind the indicator
2
Found
5 October 2026
Code
UA-2331187
Reference
2022-12-14
Reference
2022-12-26
Reference
2022-12-15
Reference
UA-P-2022-12-15-000382-b
Reference
UA-P-2022-12-28-000226-a

What stands behind it2

  1. Contract

    Date 26 December 2022 · Amount UAH 649,642 · Buyer KP "Zdolbunivvodokanal [32256482] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "DAREKS-ENERHO [39423347] · Ref UA-2022-12-28-000704-a-b1 · procedure: reporting

  2. Contract

    Date 14 December 2022 · Amount UAH 1,149,596 · Buyer KP "Zdolbunivvodokanal [32256482] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "DAREKS-ENERHO [39423347] · Ref UA-2022-12-15-001398-a-b1 · procedure: reporting

Other records of this company12

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 035 October 2026Findings · Procurement plan published late
  4. 045 October 2026Findings · Procurement plan published late
  5. 055 October 2026Findings · Procurement plan published late
  6. 064 October 2026Findings · Contract splitting on one day
  7. 074 October 2026Findings · Contract splitting on one day
  8. 084 October 2026Findings · Large contract without a procedure
  9. 094 October 2026Findings · Large contract without a procedure
  10. 104 October 2026Findings · Large contract without a procedure
All 12
  1. 114 October 2026Findings · Large contract without a procedure
  2. 124 October 2026Findings · Contract splitting under the threshold

JSONFindings · Procurement plan published late