Indicator “Procurement plan published late”: 2 contracts for 3,119,436 UAH signed 2026-08-24…2026-09-28, and the procurement plan was created later — 2026-08-26 (to 2 days after the contract); plan UA-P-2026-08-26-005783-a,UA-P-2026-09-29-000489-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "BETKOMPANI" [45182876]
EDRPOU code
45182876
Buyer
PRYVATNE AKTSIONERNE TOVARYSTVO "VOLYNOBLENERHO" [00131512]
Indicator
Procurement plan published late
Amount
UAH 3,119,436
Records behind the indicator
2
Found
5 October 2026
Code
UA-2329392
Reference
2026-08-24
Reference
2026-09-28
Reference
2026-08-26
Reference
UA-P-2026-08-26-005783-a
Reference
UA-P-2026-09-29-000489-a

What stands behind it2

  1. Contract

    45454000-4 Rekonstruktsiia (roboty z rekonstruktsii TSRP №29008 (12 cherha) dlia elektropostachannia zhytlovoho kompleksu z dytiachym doshkilnym zakladom ta mahazynom po vul. Myru, 7 v s. Lypyny Luts…

    Date 29 September 2026 · Amount UAH 1,566,803 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO "VOLYNOBLENERHO [00131512] · Ref UA-2026-09-29-000581-a-a1 · procedure: reporting

  2. Contract

    45454000-4 Rekonstruktsiia (Rekonstruktsiia elektrychnykh merezh 10/0,4kV PrAT «Volynoblenerho» dlia pryiednannia novozbudovanykh, rekonstruiovanykh chy modernizovanykh elektroustanovok zamovnyka za …

    Date 26 August 2026 · Amount UAH 1,552,633 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO "VOLYNOBLENERHO [00131512] · Ref UA-2026-08-26-004821-a-a1 · procedure: reporting

Other records of this company4

  1. 014 October 2026Findings · Duplicate records in the data
  2. 024 October 2026Findings · Contract splitting on one day
  3. 034 October 2026Findings · Large contract without a procedure
  4. 044 October 2026Findings · Contract value inflated by amendments