Ukraine · Findings · Procurement plan published late
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "AKTYVOLT" [39044710]
Why it is here
Indicator “Procurement plan published late”: 1 contracts for 1,866,534 UAH signed 2026-08-24…2026-08-24, and the procurement plan was created later — 2026-08-25 (to 1 days after the contract); plan UA-P-2026-08-25-012922-a.
The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.
Details
- Company / subject
- TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "AKTYVOLT" [39044710]
- EDRPOU code
- 39044710
- Buyer
- PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO" [00131529]
- Indicator
- Procurement plan published late
- Amount
- UAH 1,866,534
- Records behind the indicator
- 1
- Found
- 5 October 2026
- Code
- UA-2328996
- Reference
- 2026-08-24
- Reference
- 2026-08-25
- Reference
- UA-P-2026-08-25-012922-a
What stands behind it1
Contract
Budivelno-montazhni roboty dlia zovnishnoho elektropostachannia vyrobnychykh prymishchen, shcho znakhodiatsia za adresoiu: Mukachivskyi r-n, m. Mukachevo, vul. Kooperatyvna (U zv’iazku z tym, shcho v…
Date 25 August 2026 · Amount UAH 1,866,534 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO "ZAKARPATTIAOBLENERHO [00131529] · Ref UA-2026-08-25-010820-a-a1 · procedure: reporting
Other records of this company18
- 015 October 2026Findings · Procurement plan published late
- 025 October 2026Findings · Procurement plan published late
- 035 October 2026Findings · Procurement plan published late
- 044 October 2026Findings · Duplicate records in the data
- 054 October 2026Findings · Duplicate records in the data
- 064 October 2026Findings · Contract splitting on one day
- 074 October 2026Findings · Contract splitting on one day
- 084 October 2026Findings · Contract splitting on one day
- 094 October 2026Findings · Contract splitting on one day
- 104 October 2026Findings · Contract splitting on one day
All 18
- 114 October 2026Findings · Large contract without a procedure
- 124 October 2026Findings · Large contract without a procedure
- 134 October 2026Findings · Large contract without a procedure
- 144 October 2026Findings · Large contract without a procedure
- 154 October 2026Findings · Large contract without a procedure
- 164 October 2026Findings · Large contract without a procedure
- 174 October 2026Findings · Contract splitting under the threshold
- 183 October 2026Findings · Contract splitting on one day