Indicator “Procurement plan published late”: 3 contracts for 369,928,012 UAH signed 2025-12-03…2025-12-03, and the procurement plan was created later — 2025-12-05 (to 2 days after the contract); plan UA-P-2025-12-05-021987-a,UA-P-2025-12-05-022314-a,UA-P-2025-12-05-022626-a.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDALNISTIU "IEVROBUD PLIUS" [34898640]
EDRPOU code
34898640
Buyer
Sluzhba vidnovlennia ta rozvytku infrastruktury u KHarkivskii oblasti [30885376]
Indicator
Procurement plan published late
Amount
UAH 369,928,012
Records behind the indicator
3
Found
5 October 2026
Code
UA-2328125
Reference
2025-12-03
Reference
2025-12-05
Reference
UA-P-2025-12-05-021987-a
Reference
UA-P-2025-12-05-022314-a
Reference
UA-P-2025-12-05-022626-a

What stands behind it3

  1. Contract

    Date 5 December 2025 · Amount UAH 115,933,884 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u KHarkivskii oblasti [30885376] · Ref UA-2025-12-05-017449-a-b1 · procedure: reporting

  2. Contract

    Date 5 December 2025 · Amount UAH 148,198,678 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u KHarkivskii oblasti [30885376] · Ref UA-2025-12-05-017732-a-a1 · procedure: reporting

  3. Contract

    Date 5 December 2025 · Amount UAH 105,795,451 · Buyer Sluzhba vidnovlennia ta rozvytku infrastruktury u KHarkivskii oblasti [30885376] · Ref UA-2025-12-05-018023-a-c1 · procedure: reporting

Other records of this company33

  1. 015 October 2026Findings · Procurement plan published late
  2. 025 October 2026Findings · Procurement plan published late
  3. 034 October 2026Findings · Contract splitting on one day
  4. 044 October 2026Findings · Contract splitting on one day
  5. 054 October 2026Findings · Contract splitting on one day
  6. 064 October 2026Findings · Procurement under monitoring of the State Audit Service
  7. 074 October 2026Findings · Procurement under monitoring of the State Audit Service
  8. 084 October 2026Findings · Procurement under monitoring of the State Audit Service
  9. 094 October 2026Findings · Procurement under monitoring of the State Audit Service
  10. 104 October 2026Findings · Procurement under monitoring of the State Audit Service
All 33
  1. 114 October 2026Findings · Procurement under monitoring of the State Audit Service
  2. 124 October 2026Findings · Procurement under monitoring of the State Audit Service
  3. 134 October 2026Findings · Procurement under monitoring of the State Audit Service
  4. 144 October 2026Findings · Procurement under monitoring of the State Audit Service
  5. 154 October 2026Findings · Procurement under monitoring of the State Audit Service
  6. 164 October 2026Findings · Procurement under monitoring of the State Audit Service
  7. 174 October 2026Findings · Large contract without a procedure
  8. 184 October 2026Findings · Large contract without a procedure
  9. 194 October 2026Findings · Large contract without a procedure
  10. 204 October 2026Findings · Large contract without a procedure
  11. 214 October 2026Findings · Large contract without a procedure
  12. 224 October 2026Findings · Large contract without a procedure
  13. 234 October 2026Findings · Large contract without a procedure
  14. 244 October 2026Findings · Large contract without a procedure
  15. 254 October 2026Findings · Large contract without a procedure
  16. 264 October 2026Findings · Large contract without a procedure
  17. 274 October 2026Findings · Large contract without a procedure
  18. 284 October 2026Findings · Large contract without a procedure
  19. 294 October 2026Findings · Large contract without a procedure
  20. 304 October 2026Findings · Large contract without a procedure
  21. 314 October 2026Findings · Contract splitting under the threshold
  22. 324 October 2026Findings · Contract splitting under the threshold
  23. 334 October 2026Findings · Contract splitting under the threshold

JSONFindings · Procurement plan published late