Indicator “Procurement plan published late”: 3 contracts for 304,340 UAH signed 2022-12-26…2023-07-11, and the procurement plan was created later — 2022-12-28 (to 48 days after the contract); plan UA-P-2022-12-28-004930-b,UA-P-2023-07-14-001774-b,UA-P-2023-08-28-002098-b.

The procurement plan was published after the procedure had already started. Indicators computed from public data sets: contracts, payments, registers, trade and sanctions lists. An indicator is a reason to check, not a decision of a public authority.

Details

Company / subject
TOVARYSTVO Z OBMEZHENOIU VIDPOVIDA­LNISTIU «KOVINTEK» [43428681]
EDRPOU code
43428681
Buyer
PRYVATNE AKTSIONERNE TOVARYSTVO PO HAZOPOSTACHANNIU TA HAZYFIKATSII "DONETSKOBLHAZ" [03361075]
Indicator
Procurement plan published late
Amount
UAH 304,340
Records behind the indicator
3
Found
5 October 2026
Code
UA-2327998
Reference
2022-12-26
Reference
2023-07-11
Reference
2022-12-28
Reference
UA-P-2022-12-28-004930-b
Reference
UA-P-2023-07-14-001774-b
Reference
UA-P-2023-08-28-002098-b

What stands behind it3

  1. Contract

    Date 11 July 2023 · Amount UAH 168,384 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO PO HAZOPOSTACHANNIU TA HAZYFIKATSII "DONETSKOBLHAZ [03361075] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDA­LNISTIU «KOVINTEK [43428681] · Ref UA-2023-07-14-005193-a-a1 · procedure: reporting

  2. Contract

    Date 11 July 2023 · Amount UAH 133,928 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO PO HAZOPOSTACHANNIU TA HAZYFIKATSII "DONETSKOBLHAZ [03361075] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDA­LNISTIU «KOVINTEK [43428681] · Ref UA-2023-08-28-004239-a-b1 · procedure: reporting

  3. Contract

    Date 26 December 2022 · Amount UAH 2,028 · Buyer PRYVATNE AKTSIONERNE TOVARYSTVO PO HAZOPOSTACHANNIU TA HAZYFIKATSII "DONETSKOBLHAZ [03361075] · Supplier TOVARYSTVO Z OBMEZHENOIU VIDPOVIDA­LNISTIU «KOVINTEK [43428681] · Ref UA-2022-12-28-017198-a-b1 · procedure: reporting